| Project | Improvement of water supply system for Guruvayur - Package II - Phase I |
|---|---|
| Project Code | TCRGOI0917546P1 |
| Type | Package |
| Main Project | AMRUT -2016-17,2017-18 WSS to Guruvayur Municipality in Thrissur District-Improvement of water supply system for Guruvayur - Package I & II (Revised AS -81.34Cr) |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | 15MLD WTP at Kottapadi Well cum Pump house at Illikkal Transformers Pumpsets |
| Status | On-going |
| District | Thrissur |
| Executing Office | Nattika Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 131700000 |
| TS Number | TS/CE/CR/KWA/65/17-18 |
| Technical specification | Package I & II - Design ,construction and commissioning of 9m dia intake well cum pump house , 15 mld water Treatment plant, Clear water pump house at Kottapadi and supply, erection, testing and commissioning of 4 nos RW pumpsets having discharge of 95 lps against head of 62 m and 2 nos CW pump sets having discharge 182 lps against heads of 35, 2nos 500 KVA 11 KV/433 V Transformers Quantity of water to be produced-15MLD |
| Contractor | M/s Chicago constructions International pvt ltd (Mob: 9447770536) |
| Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
|---|---|---|---|---|---|---|
| 21 Jan 2021 | Pending | Pending | Risks From Other Projects | Work Completed. Commissioning cannot be done as RWPM work is not completed. | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 04/09/2018 |
|---|---|
| Scheduled date of Completion as per agreement | 03 Mar 2020 |
| Expected date of Completion | 31/12/2021 |
| TS Date | 29 Jan 2018 |
|---|---|
| Estimate Approval | 29 Jan 2018 |
| NIT Approval | 29 Jan 2018 |
| Tender Closing | 10 May 2018 |
| Technichal Pre-Qualification | 29 May 2018 |
| Price bid opening | 04 Jun 2018 |
| Workorder Date | 04 Sep 2018 |
|---|---|
| NA | 27 Sep 2018 |
| Nattika Project Dn EE |
| Date: 30/12/2023 |
Work has been completed | 100% Completed
Work completed on 30-12-2023.
| Nattika Project Dn |
| Date: 04/07/2022 |
Work has been completed | 100% Completed
Work completed except electric connection .