Project | Improvement of water supply system for Guruvayur - Package II - Phase I |
---|---|
Project Code | TCRGOI0917546P1 |
Type | Package |
Main Project | AMRUT -2016-17,2017-18 WSS to Guruvayur Municipality in Thrissur District-Improvement of water supply system for Guruvayur - Package I & II (Revised AS -81.34Cr) |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | 15MLD WTP at Kottapadi Well cum Pump house at Illikkal Transformers Pumpsets |
Status | On-going |
District | Thrissur |
Executing Office | Nattika Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 131700000 |
TS Number | TS/CE/CR/KWA/65/17-18 |
Technical specification | Package I & II - Design ,construction and commissioning of 9m dia intake well cum pump house , 15 mld water Treatment plant, Clear water pump house at Kottapadi and supply, erection, testing and commissioning of 4 nos RW pumpsets having discharge of 95 lps against head of 62 m and 2 nos CW pump sets having discharge 182 lps against heads of 35, 2nos 500 KVA 11 KV/433 V Transformers Quantity of water to be produced-15MLD |
Contractor | M/s Chicago constructions International pvt ltd (Mob: 9447770536) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
21 Jan 2021 | Pending | Pending | Risks From Other Projects | Work Completed. Commissioning cannot be done as RWPM work is not completed. | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 04/09/2018 |
---|---|
Scheduled date of Completion as per agreement | 03 Mar 2020 |
Expected date of Completion | 31/12/2021 |
TS Date | 29 Jan 2018 |
---|---|
Estimate Approval | 29 Jan 2018 |
NIT Approval | 29 Jan 2018 |
Tender Closing | 10 May 2018 |
Technichal Pre-Qualification | 29 May 2018 |
Price bid opening | 04 Jun 2018 |
Workorder Date | 04 Sep 2018 |
---|---|
NA | 27 Sep 2018 |
Nattika Project Dn |
Date: 04/07/2022 |
Work has been completed | 100% Completed
Work completed except electric connection .
Nattika Project Dn |
Date: 29/06/2022 |
Work has been completed | 100% Completed
Work completed except electric connection .