Improvement of water supply system for Guruvayur - Package II - Phase I

Project Improvement of water supply system for Guruvayur - Package II - Phase I
Project Code TCRGOI0917546P1
Type Package
Main Project AMRUT -2016-17,2017-18 WSS to Guruvayur Municipality in Thrissur District-Improvement of water supply system for Guruvayur - Package I & II (Revised AS -81.34Cr)
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description 15MLD WTP at Kottapadi Well cum Pump house at Illikkal Transformers Pumpsets
Status On-going
District Thrissur
Executing Office Nattika Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 131700000
TS Number TS/CE/CR/KWA/65/17-18
Technical specification Package I & II - Design ,construction and commissioning of 9m dia intake well cum pump house , 15 mld water Treatment plant, Clear water pump house at Kottapadi and supply, erection, testing and commissioning of 4 nos RW pumpsets having discharge of 95 lps against head of 62 m and 2 nos CW pump sets having discharge 182 lps against heads of 35, 2nos 500 KVA 11 KV/433 V Transformers Quantity of water to be produced-15MLD
Contractor M/s Chicago constructions International pvt ltd (Mob: 9447770536)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
21 Jan 2021 Pending Pending Risks From Other Projects Work Completed. Commissioning cannot be done as RWPM work is not completed. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/09/2018
Scheduled date of Completion as per agreement 03 Mar 2020
Expected date of Completion 31/12/2021

Processing Dates

TS Date 29 Jan 2018
Estimate Approval 29 Jan 2018
NIT Approval 29 Jan 2018
Tender Closing 10 May 2018
Technichal Pre-Qualification 29 May 2018
Price bid opening 04 Jun 2018

Approval Dates

Workorder Date 04 Sep 2018
NA 27 Sep 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nattika Project Dn
Date: 04/07/2022

Work has been completed | 100% Completed

Work completed except electric connection .

Nattika Project Dn
Date: 29/06/2022

Work has been completed | 100% Completed

Work completed except electric connection .