WRD 005-126-UWSS to Kothamangalam- Replacement of 300 mm AC pipe with 300 mm DI K9 from Jawahar jn to mathirappilly in kothamanagalam Municipality.
Project |
WRD 005-126-UWSS to Kothamangalam- Replacement of 300 mm AC pipe with 300 mm DI K9 from Jawahar jn to mathirappilly in kothamanagalam Municipality. |
Project Code |
EKMKIIFB0119648 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Replacement of 300 mm AC pipe with 300 mm DI K9 from Jawahar jn to mathirappilly in kothamanagalam Municipality. |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Perumbavoor Project Dn |
AS Amount (Rs) |
17900000
|
AS Number |
TRAN 2- WRD 005-126-PA-01/KIIFB |
TS Amount (Rs) |
17900000 |
TS Number |
2020/1114 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
3500 |
Capacity in MLD |
0.50 |
Actual Project Completion Date |
31 Dec 2023 |
Coverage |
MATHIRAPPILLY AREA IN KOTHAMANGALAM MUNICIPALITY |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
WRD 005-126-UWSS to Kothamangalam- Replacement of 300 mm AC pipe with 300 mm DI K9 from Jawahar jn to mathirappilly in kothamanagalam Municipality. |
Project Division Piravom(Kattapana) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Nov 2023 |
TS to be issued after getting revalidation of AS |
Piravam Project Sub Dn AE 2 |
|
24 Aug 2023 |
TS to be issued after getting revalidation of AS. |
Piravam Project Sub Dn AE 2 |
|
17 Aug 2023 |
TS to be issued after getting revalidation of AS. |
Piravam Project Sub Dn AE 2 |
|
11 Aug 2023 |
TS to be issued after getting revalidation of AS. |
Piravam Project Sub Dn AE 2 |
|
04 Aug 2023 |
TS to be issued after getting revalidation of AS. |
Piravam Project Sub Dn AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/02/2022 |
Scheduled date of Completion of the Project |
30 Jul 2022 |
Expected date of Completion |
30/06/2023 |
Processing Dates
AS Date |
17 May 2021 |
TS Date |
01 Feb 2022 |