Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DEPOSIT-Bulk meter Water Connection to Sreerosh Laurents Appartment-Bulk meter Water Connection to Sreerosh Laurents Appartment-Pipeline Work

Project DEPOSIT-Bulk meter Water Connection to Sreerosh Laurents Appartment-Bulk meter Water Connection to Sreerosh Laurents Appartment-Pipeline Work
Project Code KNRDEPO102518161P1
Type Package
Main Project DEPOSIT-Bulk meter Water Connection to Sreerosh Laurents Appartment-Bulk meter Water Connection to Sreerosh Laurents Appartment-Pipeline Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Bulk meter Water Connection to Sreerosh Laurents Appartment-Bulk meter Water Connection to Sreerosh Laurents Appartment-Pipeline Work
Status On-going
District Kannur
Executing Office Kannur WS Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 670000
TS Number 22433/2025-2026
Technical specification
Contractor Abdul Vahab.T.P. (Mob: 9895412350)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 05 Dec 2025
NIT Approval 14 Jan 2026
Tender Closing 27 Jan 2026

Approval Dates

Workorder Date 06 Feb 2026

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kannur WS Sn AE 2
Date: 25/09/2026

Work in progress | 1% Completed

Road cutting demand note issued.COP Submitted to higher office..

Kannur WS Sn AE 2
Date: 14/08/2026

Work in progress | 1% Completed

Work order issued. pipe supplied. Site handed over. Road cutting permission pending.