Project | JJM-WSS to Koratty and Kadukutty (Part) Panchayath in Thrissur district |
---|---|
Project Code | TCRJJM08207125P12 |
Type | Package |
Main Project | JJM-WSS to Koratty and Kadukutty Panchayath in Thrissur district providing FHTC and streetmain extension at Koratty Panchayath ongoing (MVS) |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-WSS to Koratty and Kadukutty (Part) Panchayath in Thrissur district |
Status | On-going |
District | Thrissur |
Executing Office | Nattika Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 128400000 |
TS Number | TS/2020-2021/2020/16697 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | 19 Aug 2022 |
Expected date of Completion | Date is not specified |
TS Date | 28 Jan 2021 |
---|---|
Estimate Approval | 28 Jan 2021 |
NIT Approval | 30 Jan 2021 |
Tender Closing | 12 Feb 2021 |
Technichal Pre-Qualification | 15 Feb 2021 |
Price bid opening | 18 Feb 2021 |
Workorder Date | 20 Feb 2021 |
---|---|
NA | 25 Feb 2021 |
Nattika Project Dn EE |
Date: 14/06/2023 |
Work in progress | 87% Completed
79 FHTC to be completed. Pipe line extension exceeded than the scheduled agreement quantity. To complete balance 79 connection more extension to be needed. So request for considering AS as final bill submitted. Bill under scruitiny under division .
Nattika Project Dn EE |
Date: 13/06/2023 |
Work in progress | 87% Completed
79 FHTC to be completed. Pipe line extension exceeded than the scheduled agreement quantity. To complete balance 79 connection more extension to be needed. So request for considering AS as final bill submitted. Bill under scruitiny under division .