AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - KANNUR MUNICIPAL AREA (OLD) - Pipeline work

Project AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - KANNUR MUNICIPAL AREA (OLD) - Pipeline work
Project Code KNRAMRUT 2032314174P1
Type Package
Main Project AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - KANNUR MUNICIPAL AREA (OLD) - Pipeline work
Funding Agency AMRUT 2
Category AMRUT 2
Type of scheme Water Supply
Scheme
Description AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - KANNUR MUNICIPAL AREA (OLD) - Pipeline work
Status On-going
District Kannur
Executing Office Kannur WS Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 23800000
TS Number WRD/KWA-CE(NR)/EST-TS/3303/2022-26-3-2
Technical specification LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - KANNUR MUNICIPAL AREA

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/06/2023
Scheduled date of Completion as per agreement 09 Mar 2024
Expected date of Completion 09/03/2024

Processing Dates

TS Date 17 Apr 2023
Estimate Approval 17 Apr 2023
NIT Approval 02 May 2023
Tender Closing 29 Apr 2023
Technichal Pre-Qualification 29 Apr 2023
Price bid opening 29 Apr 2023

Approval Dates

Workorder Date 20 May 2023
NA 31 May 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kannur WS Sn AE 2
Date: 23/06/2024

Work in progress | 23% Completed

Pipe Laid 880 m out of 3750 m and FHTC 100 Nos out of 250 Nos completed..

Kannur WS Sn AE 2
Date: 20/06/2024

Work in progress | 23% Completed

Pipe Laid 880 m out of 3750 m and FHTC 100 Nos out of 250 Nos completed..