Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

State plan-2019-20-Rural Water supply Schemes. Water supply scheme to Cheekode and adjoining villages. Package III-Laying balance distribution lines to Pulikkal and Cherukavu Panchayaths

Project State plan-2019-20-Rural Water supply Schemes. Water supply scheme to Cheekode and adjoining villages. Package III-Laying balance distribution lines to Pulikkal and Cherukavu Panchayaths
Project Code MLPGOK06202831P2
Type Package
Main Project State plan-2020-21-water supply scheme to Cheekode and adjoining villages
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Rural Water supply Schemes. Water supply scheme to Cheekode and adjoining villages. Package III-Laying balance distribution lines to Pulikkal and Cherukavu Panchayaths
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 96100000
TS Number 5040/20-21
Technical specification laying distribution network and FHTC

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/12/2020
Scheduled date of Completion as per agreement 31 Dec 2021
Expected date of Completion 31/12/2022

Processing Dates

TS Date 05 Aug 2020
Estimate Approval 05 Aug 2020
NIT Approval 12 Aug 2020
Tender Closing 25 Sep 2020
Technichal Pre-Qualification 30 Sep 2021
Price bid opening 01 Oct 2020

Approval Dates

Workorder Date 03 Nov 2020
NA 18 Dec 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE6
Date: 29/06/2024

Work in progress | 73% Completed

The work short closed as the lack of road cutting permission from PWD and shortage of GI pipe in rural concrete roads also the contractor not willing to execute the work in time extension. Estimate for the Balance works and FHTCs prepared and submitted. .

Malappuram Project Dn AE6
Date: 28/06/2024

Work in progress | 73% Completed

The work short closed as the lack of road cutting permission from PWD and shortage of GI pipe in rural concrete roads also the contractor not willing to execute the work in time extension. Estimate for the Balance works and FHTCs prepared and submitted. .