Jal Jeevan Mission - Laying distribution network and providing FHTCs in Vadavannur Grama Panchayath in Palakkad District

Project Jal Jeevan Mission - Laying distribution network and providing FHTCs in Vadavannur Grama Panchayath in Palakkad District
Project Code PKDJJM12206102
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission - Laying distribution network and providing FHTCs in Vadavannur Grama Panchayath in Palakkad District
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 165000000
AS Number 777/2020/WRD
TS Amount (Rs) 140900000
TS Number TS/2021-2022/2021/14519 Dated: 28-05-2021
Total Bill Submitted (Rs) 63174629
Total Bill Paid (Rs) 63174629
Population Benefitted 22286
Capacity in MLD 8.00
Actual Project Completion Date 31 Dec 2024
Coverage 100 lpcd

Packages

No. Project Name Location View
1 Jal Jeevan Mission - Laying distribution network and providing FHTCs in Vadavannur Grama Panchayath in Palakkad District Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Jun 2024 Work in progress | 75% Completed | 20/06/2024 Railway crossing-6 nos- permission letter received from Divisional Railway office, works branch,Palghat dtd 18/07/2023 vide letter No.RBCS ID NO SR –PGT-2023-WL-210 Total pipe laid-60.1 KM, laid/out of 80km 1). 90mm pvc 6 kg-38329m, 2) 300 mm DI-224.50m 3).250 MM DI pipe-2219.5m, 4).200 MM DI pipe-2186m 5).80mm GI-676.50M, 6).110mm pvc-12213m 7).160mm pvc 6 kg-2082M 8).100mm GI-96.00M 9).140mm pvc 6 kgc-1914m 10) 125mm GI-112M 11)300mm MS Pipe =36m 12) FHTC-1098/3096 NO Chittur Project Dn - AE 1
12 Jun 2024 Work in progress | 74% Completed | 12/06/2024 Railway crossing-6 nos- permission letter received from Divisional Railway office, works branch,Palghat dtd 18/07/2023 vide letter No.RBCS ID NO SR –PGT-2023-WL-210 Total pipe laid-59.417km, laid/out of 80km 1). 90mm pvc 6 kg-38287m, 2) 300 mm DI-197.50m 3).250 MM DI pipe-2219.5m, 4).200 MM DI pipe-2186m 5).80mm GI-676.50M, 6).110mm pvc-12171m 7).160mm pvc 6 kg-2082M 8).100mm GI-96.00M 9).140mm pvc 6 kgc-1914m 10) 125mm GI-112M 11)300mm MS Pipe =36m 12) FHTC-1098/3096 NO Chittur Project Dn - AE 1
06 Jun 2024 Work in progress | 74% Completed | 06/06/2024 Railway crossing-6 nos- permission letter received from Divisional Railway office, works branch,Palghat dtd 18/07/2023 vide letter No.RBCS ID NO SR –PGT-2023-WL-210 Total pipe laid-59.417km, laid/out of 80km 1). 90mm pvc 6 kg-38287m, 2) 300 mm DI-197.50m 3).250 MM DI pipe-2219.5m, 4).200 MM DI pipe-2186m 5).80mm GI-676.50M, 6).110mm pvc-12171m 7).160mm pvc 6 kg-2082M 8).100mm GI-96.00M 9).140mm pvc 6 kgc-1914m 10) 125mm GI-112M 11)300mm MS Pipe =36m 12) FHTC-918/3096 NO Chittur Project Dn - AE 1
29 May 2024 Work in progress | 74% Completed | 29/05/2024 Railway crossing-6 nos- permission letter received from Divisional Railway office, works branch,Palghat dtd 18/07/2023 vide letter No.RBCS ID NO SR –PGT-2023-WL-210 Total pipe laid-59.417km, laid/out of 80km 1). 90mm pvc 6 kg-38287m, 2) 300 mm DI-197.50m 3).250 MM DI pipe-2219.5m, 4).200 MM DI pipe-2186m 5).80mm GI-676.50M, 6).110mm pvc-12057m 7).160mm pvc 6 kg-2082M 8).100mm GI-96.00M 9).140mm pvc 6 kgc-1914m 10) 125mm GI-112M 11) FHTC-918/3096 NO Chittur Project Dn - AE 1
23 May 2024 Work in progress | 74% Completed | 23/05/2024 Railway crossing-6 nos- permission letter received from Divisional Railway office, works branch,Palghat dtd 18/07/2023 vide letter No.RBCS ID NO SR –PGT-2023-WL-210 Total pipe laid-59.094km, laid/out of 80km 1). 90mm pvc 6 kg-38071m, 2) 300 mm DI-197.50m 3).250 MM DI pipe-2219.5m, 4).200 MM DI pipe-2169m 5).80mm GI-676.50M, 6).110mm pvc-12051m 7).160mm pvc-2022M 8).100mm GI-96.00M 9).140mm pvc-1890m 10) 125mm GI-112M 11) FHTC-918/3096 NO Chittur Project Dn - AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 31/12/2023

Processing Dates

AS Date 24 Dec 2020
TS Date 29 Dec 2020