| Project | Deposit Work - Block Panchayath Thodupuzha- Pipe line extension to ward 12 of Arikkuzha Division (WSS to Manakkad - Laying 40mm GI Pipe from Thamala GLT to Vazhithala Koladi Road & Replacing damaged 50mm GI pipe in Thamala -Ponganpara Road. |
|---|---|
| Project Code | IDKDEPO02219117P1 |
| Type | Package |
| Main Project | Deposit Work - Block Panchayath Thodupuzha- Pipe line extension to ward 12 of Arikkuzha Division (WSS to Manakkad - Laying 40mm GI Pipe from Thamala GLT to Vazhithala Koladi Road & Replacing damaged 50mm GI pipe in Thamala -Ponganpara Road. |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | Deposit Work - Block Panchayath Thodupuzha- Pipe line extension to ward 12 of Arikkuzha Division (WSS to Manakkad - Laying 40mm GI Pipe from Thamala GLT to Vazhithala Koladi Road & Replacing damaged 50mm GI pipe in Thamala -Ponganpara Road. |
| Status | On-going |
| District | Idukki |
| Executing Office | Thodupuzha PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 500000 |
| TS Number | 4450/2021-22 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 21/02/2022 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 30/06/2022 |
| TS Date | 22 Jun 2021 |
|---|
| Thodupuzha PH Sn |
| Date: 15/10/2024 |
Work has been completed | 100% Completed
Work Completed .
| Thodupuzha PH Sn |
| Date: 08/10/2024 |
Work has started | 0% Completed
work Awarded .