| Project | NABARD-RIDF-XXII-WSS TO PATTUVAM AND ADJOINING VILLAGES (JICA AIDED) BALANCE DISTRIBUTION NETWORK - PHASE-I - ADDITIONAL WORKS ARRANGED USING BALANCE FUND |
|---|---|
| Project Code | KNRNABARD1116740P10 |
| Type | Package |
| Main Project | NABARD-RIDF-XXII-WSS TO PATTUVAM AND ADJOINING VILLAGES (JICA AIDED) BALANCE DISTRIBUTION NETWORK - PHASE-I |
| Funding Agency | NABARD |
| Category | NABARD |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-98 (01) |
| Description | By utilising balance fund, additional 11works arranged were completed |
| Status | On-going |
| District | Kannur |
| Executing Office | Kalliassery WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | |
| TS Number | |
| Technical specification | Works completed |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 28/05/2019 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 31/05/2020 |
| AS Date | 16 Nov 2016 |
|---|
| Workorder Date | 28 May 2019 |
|---|---|
| NA | 21 Jun 2019 |
| Thaliparamba WS Dn EE |
| Date: 11/01/2023 |
Work has been completed | 100% Completed
work completed. Final bill paid.
| Thaliparamba WS Dn EE |
| Date: 12/10/2021 |
Work has been completed | 100% Completed
Final bill under scrutiny.