| Project | Deposit-US-Work under SC development Ambedkar Grama Vikasana Programme at Kundayittammal colony Concrete road: from Shanmuga house to Kunnath Ambootty house(Water tank road) |
|---|---|
| Project Code | KNRGOK022618321P1 |
| Type | Package |
| Main Project | Deposit-US-Work under SC development Ambedkar Grama Vikasana Programme at Kundayittammal colony Concrete road: from Shanmuga house to Kunnath Ambootty house(Water tank road) |
| Funding Agency | GOK |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | Deposit-US-Work under SC development Ambedkar Grama Vikasana Programme at Kundayittammal colony Concrete road: from Shanmuga house to Kunnath Ambootty house(Water tank road) |
| Status | On-going |
| District | Kannur |
| Executing Office | Pilathra WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 207000 |
| TS Number | WRD/KWA-CE(NR)/EST/25615/2024_26_1_1 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | Date is not specified |
| TS Date | 16 Feb 2026 |
|---|---|
| Estimate Approval | 16 Feb 2026 |
| NIT Approval | 16 Feb 2026 |
| Pilathara WS Sn - AE |
| Date: 25/05/2026 |
Work has started | 0% Completed
Tender stage.
| Thaliparamba WS Dn EE |
| Date: 19/05/2026 |
Work has started | 0% Completed
Tendered. No offer received..