JJM-2022-23 WSS to Madakkathara Panchayath -Providing Distribution Network and FHTC to Pananchery panchayath

Project JJM-2022-23 WSS to Madakkathara Panchayath -Providing Distribution Network and FHTC to Pananchery panchayath
Project Code TCRJJM052213966P1
Type Package
Main Project JJM-2022-23 WSS to Madakkathara Panchayath -Providing Distribution Network and FHTC to Pananchery Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission JJM-2022-23-WSS to Pananchery , Puthur and Madakkathara panchayaths in Thrissur district-Providing distribution network and FHTC to Pananchery Panchayath-Pipe line work
Status On-going
District Thrissur
Executing Office Nattika Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 771300000
TS Number WRD/KWA-CE(CR)/EST_TS/13397/2022_26_1_1
Technical specification Jal Jeevan Mission JJM-2022-23-WSS to Pananchery , Puthur and Madakkathara panchayaths in Thrissur district-Providing distribution network and FHTC to Pananchery Panchayath-Pipe line work
Contractor Reena Engineers and Contractors Pvt.Ltd (Mob: 9447026559)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 16/03/2023
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 17/09/2024

Processing Dates

TS Date 20 Dec 2022
Estimate Approval 20 Dec 2022
NIT Approval 23 Dec 2022
Technichal Pre-Qualification 18 Jan 2023
Price bid opening 09 Feb 2023

Approval Dates

Workorder Date 16 Mar 2023
NA 31 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nattika Project Dn EE
Date: 11/03/2025

Work in progress | 48% Completed

cumulative supply -227096.5 M /227096.5 M . Laid total = 112452.48 M/224125.5M . HTC given :2119/ 7169 Nos. Geotagging : 2096/7169 Nos . Road Restoration - Partial restoration by GSB/WMM for BT cutting:-Today - 0 M,Cumulative- 0 M / M ,Berm restoration by GSB:-Today - 0 M,Cumulative :- 0/ 102510.76 M,BT restoration:-Today – 0 Cumulative :-0/ 110672.98M, Earthen road restoration :-Today - 0mCumulative :- 0 M / 110672.98M ,restoration by PCC(concrete)Today - 0 M,Cumulative :-1428.3 M/110672.98M,WMM ,Today : 0 M,Cumulative :- 1633.9M, geotrack mapping today 0 m cumulative : 92491.8 m/110672.98M.

Nattika Project Dn EE
Date: 10/03/2025

Work in progress | 47% Completed

cumulative supply -227096.5 M /227096.5 M . Laid total = 111865.68 M/224125.5M . HTC given : 2114/ 7169 Nos. Geotagging : 2090/7169 Nos . Road Restoration - Partial restoration by GSB/WMM for BT cutting:-Today - 0 M,Cumulative- 0 M / M ,Berm restoration by GSB:-Today - 0 M,Cumulative :- 0/ 102510.76 M,BT restoration:-Today – 0 Cumulative :-0/ 110672.98M, Earthen road restoration :-Today - 0mCumulative :- 0 M / 110672.98M ,restoration by PCC(concrete)Today - 0 M,Cumulative :-1428.3 M/110672.98M,WMM ,Today : 0 M,Cumulative :- 1633.9M, geotrack mapping today 0 m cumulative : 92491.8 m/110672.98M.