Project | JJM-2022-23 WSS to Madakkathara Panchayath -Providing Distribution Network and FHTC to Pananchery panchayath |
---|---|
Project Code | TCRJJM052213966P1 |
Type | Package |
Main Project | JJM-2022-23 WSS to Madakkathara Panchayath -Providing Distribution Network and FHTC to Pananchery Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Jal Jeevan Mission JJM-2022-23-WSS to Pananchery , Puthur and Madakkathara panchayaths in Thrissur district-Providing distribution network and FHTC to Pananchery Panchayath-Pipe line work |
Status | On-going |
District | Thrissur |
Executing Office | Nattika Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 771300000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/13397/2022_26_1_1 |
Technical specification | Jal Jeevan Mission JJM-2022-23-WSS to Pananchery , Puthur and Madakkathara panchayaths in Thrissur district-Providing distribution network and FHTC to Pananchery Panchayath-Pipe line work |
Contractor | Reena Engineers and Contractors Pvt.Ltd (Mob: 9447026559) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 16/03/2023 |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | 17/09/2024 |
TS Date | 20 Dec 2022 |
---|---|
Estimate Approval | 20 Dec 2022 |
NIT Approval | 23 Dec 2022 |
Technichal Pre-Qualification | 18 Jan 2023 |
Price bid opening | 09 Feb 2023 |
Workorder Date | 16 Mar 2023 |
---|---|
NA | 31 Mar 2023 |
Nattika Project Dn EE |
Date: 11/03/2025 |
Work in progress | 48% Completed
cumulative supply -227096.5 M /227096.5 M . Laid total = 112452.48 M/224125.5M . HTC given :2119/ 7169 Nos. Geotagging : 2096/7169 Nos . Road Restoration - Partial restoration by GSB/WMM for BT cutting:-Today - 0 M,Cumulative- 0 M / M ,Berm restoration by GSB:-Today - 0 M,Cumulative :- 0/ 102510.76 M,BT restoration:-Today – 0 Cumulative :-0/ 110672.98M, Earthen road restoration :-Today - 0mCumulative :- 0 M / 110672.98M ,restoration by PCC(concrete)Today - 0 M,Cumulative :-1428.3 M/110672.98M,WMM ,Today : 0 M,Cumulative :- 1633.9M, geotrack mapping today 0 m cumulative : 92491.8 m/110672.98M.
Nattika Project Dn EE |
Date: 10/03/2025 |
Work in progress | 47% Completed
cumulative supply -227096.5 M /227096.5 M . Laid total = 111865.68 M/224125.5M . HTC given : 2114/ 7169 Nos. Geotagging : 2090/7169 Nos . Road Restoration - Partial restoration by GSB/WMM for BT cutting:-Today - 0 M,Cumulative- 0 M / M ,Berm restoration by GSB:-Today - 0 M,Cumulative :- 0/ 102510.76 M,BT restoration:-Today – 0 Cumulative :-0/ 110672.98M, Earthen road restoration :-Today - 0mCumulative :- 0 M / 110672.98M ,restoration by PCC(concrete)Today - 0 M,Cumulative :-1428.3 M/110672.98M,WMM ,Today : 0 M,Cumulative :- 1633.9M, geotrack mapping today 0 m cumulative : 92491.8 m/110672.98M.