AMRUT2016-17 - Providing new net work in the missing area of core city

Project AMRUT2016-17 - Providing new net work in the missing area of core city
Project Code TVMAMRUT1117889
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT - Providing new net work in the missing area of core city GO(Rt)No.3530/2017/LSGD DATED 02/11/2017 OF LOCAL SELF GOVT (DC) DEPARTMENT PROVIDING NEW NET WORK IN THE MISSING AREAS OF THE CORE CITY IN THIRUVANANTHAPURAM AMOUNT-7.98 Cr.
Status On-going
District Thiruvananthapuram
Executing Office Pattoor Sewerage Dn
AS Amount (Rs) 79800000
AS Number 317/LSGD dt 02117 revalidated 687/2021/LSGD dt 10/03/2021,1939/2020/LSGD dt 16/10/2020 vattavila
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs) 35039508
Total Bill Paid (Rs) 35039508
Population Benefitted 15000
Capacity in MLD 2.00
Actual Project Completion Date 31 Dec 2021
Coverage Jagathy Ward (Partial)
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Supplying and laying 200 mm dia SW sewer line from The Existing MH towards Binoy lane at Kizhakke Pattom Residence Association Pattoor Sewerage Dn
2 TSS- D Block zone II - Laying 600mm dia RCC NP3 pipe sewer main from Edappazhinji to Chithranagar via vettamukku.-Reach1 Pattoor Sewerage Dn
3 TSS- D Block zone II - Laying 600mm dia RCC NP3 pipe sewer main from Edappazhinji to Chithranagar via vettamukku.-Reach2 Pattoor Sewerage Dn
4 TSS- E Block Zone III - Supplying and laying 150 mm dia SW branch sewer line from the existing MH towards Melekuzhivila at Maruthamkuzhy Pattoor Sewerage Dn
5 TSS- E Block Zone III - Supplying and laying 200 mm dia SW pipe branch sewer line from the existing Konathukulangara lane towards Padayani road ( PRA - lane10) at Maruthankuzhy Pattoor Sewerage Dn
6 TSS- E Block Zone III - Supplying and laying 200 mm dia SW pipe branch sewer line from the existing Konathukulangara line towards Padayani road association lane No. 05 ( PRA 16-20) at Maruthankuzhy Pattoor Sewerage Dn
7 TSS- E Block Zone III - Supplying and laying 200 mm dia SW pipe branch sewer line from the existing Konathukulangara sewer main towards Dwani Lane ( PRA Lane No.07) at Maruthankuzhy. Pattoor Sewerage Dn
8 TSS E Block Zone II- Laying 300mm dia SW Pipe sewer main from Jagathy Vettamukku sewer main MH 60 towards Koottamvila Ex.MH (N-N1) Pattoor Sewerage Dn
9 TSS - E Block Zone II - Laying 300mm dia SW Sewer main interconnection between Kootanvila and Chittatinkara Sewer main. Pattoor Sewerage Dn
10 Tss- E Block Zone II - Laying 700mm dia sewer main from Jagathy towards common manhole at Vivekananda Nagar IInd Reach ch 259m to 512m Plamoodu project Sn
11 Tss- E Block Zone II - Laying 700mm dia sewer main from Jagathy towards common manhole at Vivekananda Nagar Ist Reach ch 0m to 259m Plamoodu project Sn
12 TSS - Laying 250 mm dia DI K9 pumping main from Mudavanmugal Pump House to Jagathy Junction and construction of Stilling Chamber at Jagathy Junction Sewerage Section 2, Kuriathy Kuriathy Sewerage Sn 2
13 TSS-Supplying and laying 200 mm dia SW pipe sewer line from Padayani Road Ex: MH towards Padayani Gardens Lane No. 8A ( PRA G1 to G17) Pattoor Sewerage Dn
14 TSS-Urgent laying of 300mm dia SW pipe and construction of new manholes at Chengalloor and Vattavila of Punnakkamugal ward. Kuriathy Sewerage Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Feb 2024 Direction received from the EE, Sewerage Division, Pattoor for closing the work vide letter no: KWA/SD/DB/1409/2018 dated 11 12 2023. Kuriathy Sewerage Sn2 AE
24 Jan 2024 Direction received from the EE, Sewerage Division, Pattoor for closing the work vide letter no: KWA/SD/DB/1409/2018 dated 11 12 2023. Kuriathy Sewerage Sn2 AE
01 Dec 2023 For laying the remaining pipe line, PWD road cutting sanction for roads under DLP is required (Jagathy - Poojappura road) Kuriathy Sewerage Sn2 AE
07 Sep 2023 For laying the remaining pipe line, PWD road cutting sanction for roads under DLP is required (Jagathy - Poojappura road) Kuriathy Sewerage Sn2 AE
17 Aug 2023 For laying the remaining pipe line, PWD road cutting sanction for roads under DLP is required (Jagathy - Poojappura road) Kuriathy Sewerage Sn2 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 05/01/2018
Scheduled date of Completion of the Project 31 Dec 2021
Expected date of Completion 31/03/2023

Processing Dates

AS Date 02 Nov 2017
TS Date 22 Mar 2018

Other details