AMRUT2016-17 - Providing new net work in the missing area of core city
Project |
AMRUT2016-17 - Providing new net work in the missing area of core city |
Project Code |
TVMAMRUT1117889 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT - Providing new net work in the missing area of core city
GO(Rt)No.3530/2017/LSGD DATED 02/11/2017 OF LOCAL SELF GOVT (DC) DEPARTMENT
PROVIDING NEW NET WORK IN THE MISSING AREAS OF THE CORE CITY IN THIRUVANANTHAPURAM
AMOUNT-7.98 Cr. |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Pattoor Sewerage Dn |
AS Amount (Rs) |
79800000
|
AS Number |
317/LSGD dt 02117 revalidated 687/2021/LSGD dt 10/03/2021,1939/2020/LSGD dt 16/10/2020 vattavila |
TS Amount (Rs) |
|
TS Number |
|
Total Bill Submitted (Rs) |
35039508 |
Total Bill Paid (Rs) |
35039508 |
Population Benefitted |
15000 |
Capacity in MLD |
2.00 |
Actual Project Completion Date |
31 Dec 2021 |
Coverage |
Jagathy Ward (Partial) |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Supplying and laying 200 mm dia SW sewer line from The Existing MH towards Binoy lane at Kizhakke Pattom Residence Association |
Pattoor Sewerage Dn |
|
2 |
TSS- D Block zone II - Laying 600mm dia RCC NP3 pipe sewer main from Edappazhinji to Chithranagar via vettamukku.-Reach1 |
Pattoor Sewerage Dn |
|
3 |
TSS- D Block zone II - Laying 600mm dia RCC NP3 pipe sewer main from Edappazhinji to Chithranagar via vettamukku.-Reach2 |
Pattoor Sewerage Dn |
|
4 |
TSS- E Block Zone III - Supplying and laying 150 mm dia SW branch sewer line from the existing MH towards Melekuzhivila at Maruthamkuzhy |
Pattoor Sewerage Dn |
|
5 |
TSS- E Block Zone III - Supplying and laying 200 mm dia SW pipe branch sewer line from the existing Konathukulangara lane towards Padayani road ( PRA - lane10) at Maruthankuzhy |
Pattoor Sewerage Dn |
|
6 |
TSS- E Block Zone III - Supplying and laying 200 mm dia SW pipe branch sewer line from the existing Konathukulangara line towards Padayani road association lane No. 05 ( PRA 16-20) at Maruthankuzhy |
Pattoor Sewerage Dn |
|
7 |
TSS- E Block Zone III - Supplying and laying 200 mm dia SW pipe branch sewer line from the existing Konathukulangara sewer main towards Dwani Lane ( PRA Lane No.07) at Maruthankuzhy. |
Pattoor Sewerage Dn |
|
8 |
TSS E Block Zone II- Laying 300mm dia SW Pipe sewer main from Jagathy Vettamukku sewer main MH 60 towards Koottamvila Ex.MH (N-N1) |
Pattoor Sewerage Dn |
|
9 |
TSS - E Block Zone II - Laying 300mm dia SW Sewer main interconnection between Kootanvila and Chittatinkara Sewer main. |
Pattoor Sewerage Dn |
|
10 |
Tss- E Block Zone II - Laying 700mm dia sewer main from Jagathy towards common manhole at Vivekananda Nagar IInd Reach ch 259m to 512m |
Plamoodu project Sn |
|
11 |
Tss- E Block Zone II - Laying 700mm dia sewer main from Jagathy towards common manhole at Vivekananda Nagar Ist Reach ch 0m to 259m |
Plamoodu project Sn |
|
12 |
TSS - Laying 250 mm dia DI K9 pumping main from Mudavanmugal Pump House to Jagathy Junction and construction of Stilling Chamber at Jagathy Junction Sewerage Section 2, Kuriathy |
Kuriathy Sewerage Sn 2 |
|
13 |
TSS-Supplying and laying 200 mm dia SW pipe sewer line from Padayani Road Ex: MH towards Padayani Gardens Lane No. 8A ( PRA G1 to G17) |
Pattoor Sewerage Dn |
|
14 |
TSS-Urgent laying of 300mm dia SW pipe and construction of new manholes at Chengalloor and Vattavila of Punnakkamugal ward. |
Kuriathy Sewerage Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Feb 2024 |
Direction received from the EE, Sewerage Division, Pattoor for closing the work vide letter no: KWA/SD/DB/1409/2018 dated 11 12 2023. |
Kuriathy Sewerage Sn2 AE |
|
24 Jan 2024 |
Direction received from the EE, Sewerage Division, Pattoor for closing the work vide letter no: KWA/SD/DB/1409/2018 dated 11 12 2023. |
Kuriathy Sewerage Sn2 AE |
|
01 Dec 2023 |
For laying the remaining pipe line, PWD road cutting sanction for roads under DLP is required (Jagathy - Poojappura road)
|
Kuriathy Sewerage Sn2 AE |
|
07 Sep 2023 |
For laying the remaining pipe line, PWD road cutting sanction for roads under DLP is required (Jagathy - Poojappura road) |
Kuriathy Sewerage Sn2 AE |
|
17 Aug 2023 |
For laying the remaining pipe line, PWD road cutting sanction for roads under DLP is required (Jagathy - Poojappura road) |
Kuriathy Sewerage Sn2 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
05/01/2018 |
Scheduled date of Completion of the Project |
31 Dec 2021 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
02 Nov 2017 |
TS Date |
22 Mar 2018 |