- Home
- JJM -2021-22-Phase III- Laying pipes and...
JJM -2021-22-Phase III- Laying pipes and providing functional household tap connection in Kooroppada Panchayath, Kottayam District.
Project |
JJM -2021-22-Phase III- Laying pipes and providing functional household tap connection in Kooroppada Panchayath, Kottayam District. |
Project Code |
KTMJJM022212302 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM -2021-22-Phase III- Laying pipes and providing functional household tap connection in Kooroppada Panchayath, Kottayam District. |
Status |
On-going |
District |
Kottayam |
Executing Office |
Kottayam PH Dn |
AS Amount (Rs) |
850900000
|
AS Number |
GO(Rt)No.134/2022/WRD |
TS Amount (Rs) |
560100000 |
TS Number |
TS/2022-2023/2022/26055 |
Total Bill Submitted (Rs) |
1 |
Total Bill Paid (Rs) |
1 |
Population Benefitted |
25670 |
Capacity in MLD |
4.00 |
Actual Project Completion Date |
13 May 2024 |
Coverage |
Kooroppad Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM -2021-22-Phase III- Laying pipes and providing functional household tap connection in Kooroppada Panchayath, Kottayam District. |
Thiruvanchoor WW Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Dec 2022 |
Agreement executed on 30.11.2022 |
Kottayam PH Dn EE |
|
14 Nov 2022 |
Work order issued on 14.11.2022. |
Kottayam PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
23/02/2022 |
Scheduled date of Completion of the Project |
13 May 2024 |
Expected date of Completion |
13/05/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
07 Jul 2022 |