JJM- Providing FHTC from WSS to Mg Kavu pth in Tcr dist- Phase 2-Laying of 200mm DI k9 pipe clear water pumping main from GLSR near Poomla dam to OHSR at chottupara-5th SLSSC Package 8-pipeline work

Project JJM- Providing FHTC from WSS to Mg Kavu pth in Tcr dist- Phase 2-Laying of 200mm DI k9 pipe clear water pumping main from GLSR near Poomla dam to OHSR at chottupara-5th SLSSC Package 8-pipeline work
Project Code TCRJJM022213936P5
Type Package
Main Project Jal Jeevan Mission (JJM)-5th SLSSC -Water Supply Scheme to Mulamkunnathukavu Grama Panchayath in Thrissur District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM- Providing FHTC from WSS to Mg Kavu pth in Tcr dist- Phase 2-Laying of 200mm DI k9 pipe clear water pumping main from GLSR near Poomla dam to OHSR at chottupara-5th SLSSC Package 8-pipeline work
Status On-going
District Thrissur
Executing Office Thrissur WW Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 6090000
TS Number WRD/KWA-CE(CR)/EST_TS/16899/2022_26_1_1 dtd6.6.2023
Technical specification Laying of 200mm DI k9 pipe clear water pumping main from GLSR near Poomla dam to OHSR at chottupara-5th SLSSC Package 8-pipeline work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 16/08/2023
Scheduled date of Completion as per agreement 05 Sep 2023
Expected date of Completion 31/03/2024

Processing Dates

TS Date 06 Jun 2023
Estimate Approval 06 Jun 2023
NIT Approval 22 Jun 2023
Tender Closing 06 Jul 2023
Technichal Pre-Qualification 06 Jul 2023
Price bid opening 07 Jul 2023

Approval Dates

Workorder Date 16 Aug 2023
NA 23 Aug 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thrissur WW Sn - AE 1
Date: 25/06/2024

Work has been completed | 100% Completed

Work completed. Bill submitted..

Thrissur WW Sn - AE 1
Date: 27/05/2024

Work has been completed | 100% Completed

Chamber work completed, Air valve, Scour valve fixing work completed. Bill under preparation..