Deposit work-2020-21-KWA-MCH Urgent Rectification works Construction of RCC Manholes and Relaying the damaged sewer main and allied works in back side of Mens Hostel 1 to 3 at MC campus.

Project Deposit work-2020-21-KWA-MCH Urgent Rectification works Construction of RCC Manholes and Relaying the damaged sewer main and allied works in back side of Mens Hostel 1 to 3 at MC campus.
Project Code TVMGOK08206041P17
Type Package
Main Project Deposit Work-2020-21-KWA Medical college
Funding Agency GOK
Category Deposit Work
Type of scheme Water Supply
Scheme 4215-01-800-89
Description KWA-MCH Urgent Rectification works Construction of RCC Manholes and Relaying the damaged sewer main and allied works in back side of Mens Hostel 1 to 3 at MC campus.
Status On-going
District Thiruvananthapuram
Executing Office TVM Medical College Sn
Agreement Number
Agreement Date
TS Amount (Rs) 1368593
TS Number 15254/2020-2021
Technical specification Urgent Rectification works Construction of RCC Manholes and Relaying the damaged sewer main and allied works in back side of Mens Hostel 1 to 3 at MC campus.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 26/02/2021
Scheduled date of Completion as per agreement 26 May 2021
Expected date of Completion 31/08/2021

Processing Dates

TS Date 25 Jan 2021
Estimate Approval 25 Jan 2021
NIT Approval 27 Jan 2021
Tender Closing 08 Feb 2021
Technichal Pre-Qualification 11 Feb 2021
Price bid opening 11 Feb 2021

Approval Dates

Workorder Date 26 Feb 2021
NA 04 Mar 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thiruvananthapuram - Med col - AE
Date: 21/10/2021

Work has been completed | 100% Completed

Work completed .

Thiruvananthapuram - Med col - AE
Date: 18/10/2021

Work has been completed | 100% Completed

Work completed.