| Project | AMRUT 2.0 - last mile connectivity -Balance work- Laying pipelines at various wards in Old Muncipal area in Kollam corporation for providing house connection (FHTCs) -pipeline work WSS 1 |
|---|---|
| Project Code | KLMAMRUT 2112215331P1 |
| Type | Package |
| Main Project | AMRUT 2.0 - last mile connectivity -Balance work- Laying pipelines at various wards in Old Muncipal area in Kollam corporation for providing house connection (FHTCs) -pipeline work WSS 1 |
| Funding Agency | AMRUT 2 |
| Category | AMRUT 2 |
| Type of scheme | Water Supply |
| Scheme | |
| Description | AMRUT 2.0 - last mile connectivity -Balance work- Laying pipelines at various wards in Old Municipal area in Kollam corporation for providing house connection (FHTCs) -pipeline work |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam WS Sn 1 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | |
| TS Number | WRD/KW-CE(SR)/TS/13262/2022 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 07/12/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 06 Jun 2024 |
| Expected date of Completion | 06/06/2024 |
| TS Date | 12 Jul 2023 |
|---|---|
| Price bid opening | 31 Jul 2023 |
| Workorder Date | 05 Dec 2023 |
|---|---|
| NA | 07 Dec 2023 |
| Kollam WS Sn 1 - AE |
| Date: 02/03/2026 |
Work has been completed | 100% Completed
100% work completed and final bill submitted.63mm PVC pipe-220m and 75mm PVC pipe -200m are balance with contractor..
| Kollam WS Sn 1 - AE |
| Date: 13/02/2026 |
Work in progress | 99% Completed
99 % completed, 4600 m/4600m pipe laid, 236 nos alterations are given.