JJM 2022 - 2024 VILAPPIL GRAMA PANCHAYATH - PROVIDING WATER SUPPLY TO KADUMBUHILLS 1000 FHTCS CONSTRUCTION OF SUMP CUM PUMP HOUSE 1LL OHSR PUMPING MAIN PROVIDING PUMPS AND DISTRIBUTION LINES AND DISTRIBUTION LINES - GENERAL CIVIL WORK.

Project JJM 2022 - 2024 VILAPPIL GRAMA PANCHAYATH - PROVIDING WATER SUPPLY TO KADUMBUHILLS 1000 FHTCS CONSTRUCTION OF SUMP CUM PUMP HOUSE 1LL OHSR PUMPING MAIN PROVIDING PUMPS AND DISTRIBUTION LINES AND DISTRIBUTION LINES - GENERAL CIVIL WORK.
Project Code TVMJJM022213805
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM 2022 - 2024 VILAPPIL GRAMA PANCHAYATH - PROVIDING WATER SUPPLY TO KADUMBUHILLS 1000 FHTCS CONSTRUCTION OF SUMP CUM PUMP HOUSE 1LL OHSR PUMPING MAIN PROVIDING PUMPS AND DISTRIBUTION LINES AND DISTRIBUTION LINES - GENERAL CIVIL WORK.
Status On-going
District Thiruvananthapuram
Executing Office Aruvikkara HW Dn
AS Amount (Rs) 97468000
AS Number GO (Rt) No 134/2022/WRD
TS Amount (Rs) 67460000
TS Number 8804/2022-2023
Total Bill Submitted (Rs) 161
Total Bill Paid (Rs) 161
Population Benefitted 5000
Capacity in MLD 10.00
Actual Project Completion Date 31 Mar 2024
Coverage 1000 FHTCs
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM 2022 - 2024 VILAPPIL GRAMA PANCHAYATH - PROVIDING WATER SUPPLY TO KADUMBUHILLS 1000 FHTCS CONSTRUCTION OF SUMP CUM PUMP HOUSE 1LL OHSR PUMPING MAIN PROVIDING PUMPS AND DISTRIBUTION LINES AND DISTRIBUTION LINES - GENERAL CIVIL WORK. Aryanad WW Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Feb 2024 Column work completed Aryanad AE
26 Dec 2023 Column work started Aryanad AE
06 Dec 2023 Footing Concrete work starte Aryanad AE
14 Nov 2023 pipe laying works ongoing Aryanad AE
24 Mar 2023 WORK ORDER ISSUED Aruvikkara HW Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/03/2023
Scheduled date of Completion of the Project 31 Dec 2023
Expected date of Completion 31/03/2024

Processing Dates

AS Date 23 Feb 2021
TS Date 17 Dec 2022

Other details

Project Officers View