- Home
- DEPOSIT-PWD-CWSS to Oachira and Adjoinin...
DEPOSIT-PWD-CWSS to Oachira and Adjoining Panchayaths-Replacing damaged 90mm PVC pipe line and leak rectification in 80mm CI pipe line during drainage work of PWD road (Oachira Kochumuri Puthanveettil Junction Road) in Oachira Panchayath-General Civil Work
| Project |
DEPOSIT-PWD-CWSS to Oachira and Adjoining Panchayaths-Replacing damaged 90mm PVC pipe line and leak rectification in 80mm CI pipe line during drainage work of PWD road (Oachira Kochumuri Puthanveettil Junction Road) in Oachira Panchayath-General Civil Work |
| Project Code |
KLMDEPO082618433 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
DEPOSIT-PWD-CWSS to Oachira and Adjoining Panchayaths-Replacing damaged 90mm PVC pipe line and leak rectification in 80mm CI pipe line during drainage work of PWD road (Oachira Kochumuri Puthanveettil Junction Road) in Oachira Panchayath-General Civil Work |
| Status |
Completed |
| District |
Kollam |
| Executing Office |
Chavara PH Sub Dn |
| AS Amount (Rs) |
17000
|
| AS Number |
XUTR/RBISH00809992486 |
| TS Amount (Rs) |
17100 |
| TS Number |
14328/2026-2027 |
| Total Bill Submitted (Rs) |
1 |
| Total Bill Paid (Rs) |
1 |
| Population Benefitted |
25 |
| Capacity in MLD |
0.20 |
| Actual Project Completion Date |
01 Oct 2026 |
| Coverage |
Oachira Kochumuri Puthanveettil Junction Road |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
DEPOSIT-PWD-CWSS to Oachira and Adjoining Panchayaths-Replacing damaged 90mm PVC pipe line and leak rectification in 80mm CI pipe line during drainage work of PWD road (Oachira Kochumuri Puthanveettil Junction Road) in Oachira Panchayath-General Civil Work |
Oachira PH Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 01 Oct 2026 |
Work completed |
Oachira AE |
|
| 30 Sep 2026 |
Work ongoing |
Oachira AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
30/09/2026 |
| Scheduled date of Completion of the Project |
01 Oct 2026 |
| Expected date of Completion |
01/10/2026 |
Processing Dates
| TS Date |
28 Sep 2026 |
| AS Date |
18 Aug 2026 |