Jal Jeevan Mission (JJM) - Padiyur Grama Panchayath - Extension of pipe line from Aripalam bridge to Mathilakam bridge - at Padiyur Grama Panchayath - Pipeline Work.

Project Jal Jeevan Mission (JJM) - Padiyur Grama Panchayath - Extension of pipe line from Aripalam bridge to Mathilakam bridge - at Padiyur Grama Panchayath - Pipeline Work.
Project Code TCRJJM08203903P4
Type Package
Main Project JJM - Padiyur GramaPanchayath - RDWSS to Karalam, Kattoor, Padiyoor, Poomangalam - Providing FHTC to Rural house holds
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM) - Padiyur Grama Panchayath - Extension of pipe line from Aripalam bridge to Mathilakam bridge - at Padiyur Grama Panchayath - Pipeline Work.
Status On-going
District Thrissur
Executing Office Irinjalakkuda PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 950000
TS Number WRD/KWA-CE(CR)/EST_TS/17978/2023_26_1_1
Technical specification Jal Jeevan Mission (JJM) - Padiyur Grama Panchayath - Extension of pipe line from Aripalam bridge to Mathilakam bridge - at Padiyur Grama Panchayath - Pipeline Work.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 23/02/2022
Scheduled date of Completion as per agreement 13 Dec 2023
Expected date of Completion Date is not specified

Processing Dates

TS Date 09 Aug 2023
Estimate Approval 09 Aug 2023
NIT Approval 09 Aug 2023
Tender Closing 24 Aug 2023
Price bid opening 24 Aug 2023

Approval Dates

Workorder Date 24 Aug 2023
NA 05 Sep 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Irinjalakuda AE
Date: 27/06/2024

Work has started | 0% Completed

Dropped due to non-cutting permission from NH.

Irinjalakuda AE
Date: 26/06/2024

Work has started | 0% Completed

Dropped due to non-cutting permission from NH.