Project | Jal Jeevan Mission (JJM) - Padiyur Grama Panchayath - Extension of pipe line from Aripalam bridge to Mathilakam bridge - at Padiyur Grama Panchayath - Pipeline Work. |
---|---|
Project Code | TCRJJM08203903P4 |
Type | Package |
Main Project | JJM - Padiyur GramaPanchayath - RDWSS to Karalam, Kattoor, Padiyoor, Poomangalam - Providing FHTC to Rural house holds |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM) - Padiyur Grama Panchayath - Extension of pipe line from Aripalam bridge to Mathilakam bridge - at Padiyur Grama Panchayath - Pipeline Work. |
Status | On-going |
District | Thrissur |
Executing Office | Irinjalakkuda PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 950000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/17978/2023_26_1_1 |
Technical specification | Jal Jeevan Mission (JJM) - Padiyur Grama Panchayath - Extension of pipe line from Aripalam bridge to Mathilakam bridge - at Padiyur Grama Panchayath - Pipeline Work. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 23/02/2022 |
---|---|
Scheduled date of Completion as per agreement | 13 Dec 2023 |
Expected date of Completion | Date is not specified |
TS Date | 09 Aug 2023 |
---|---|
Estimate Approval | 09 Aug 2023 |
NIT Approval | 09 Aug 2023 |
Tender Closing | 24 Aug 2023 |
Price bid opening | 24 Aug 2023 |
Workorder Date | 24 Aug 2023 |
---|---|
NA | 05 Sep 2023 |
Irinjalakuda AE |
Date: 27/06/2024 |
Work has started | 0% Completed
Dropped due to non-cutting permission from NH.
Irinjalakuda AE |
Date: 26/06/2024 |
Work has started | 0% Completed
Dropped due to non-cutting permission from NH.