PACKAGE - II-Supply and errection of raw water pumpset , transformer and construction of substation building and alied works ,supply and laying raw water pumping main ,clear water pumping main and construction of 11 lakh lite capacity OHSR at Bovikkanam in Kasaragod district
Project |
PACKAGE - II-Supply and errection of raw water pumpset , transformer and construction of substation building and alied works ,supply and laying raw water pumping main ,clear water pumping main and construction of 11 lakh lite capacity OHSR at Bovikkanam in Kasaragod district |
Project Code |
KGDKIIFB0117579P1 |
Type |
Package |
Main Project |
KIIFB-WSS TO KASARAGOD MUNICIPALITY AND CHEMMANAD PANCHAYATH - PHASE I
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Supply and erection of raw water pump set , transformer and construction of substation building and allied works ,supply and laying raw water pumping main ,clear water pumping main and construction of 11 lakh litre capacity OHSR at Bovikkanam |
Status |
On-going |
District |
Kasaragod |
Executing Office |
Project Division Kannur ( KGD) |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
760000000 |
TS Number |
KWA/CE/NR/45/2016-17 |
Technical specification |
Supply and erection of raw water pump set , transformer and construction of substation building and allied works ,supply and laying raw water pumping main ,clear water pumping main and construction of 11 lakh litre capacity OHSR at Bovikkanam |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
11/08/2017 |
Scheduled date of Completion as per agreement |
19 Jul 2018 |
Expected date of Completion |
30/10/2021 |
Processing Dates
TS Date |
03 Mar 2017 |
Estimate Approval |
20 Mar 2017 |
NIT Approval |
04 Apr 2017 |
Tender Closing |
20 Apr 2017 |
Technichal Pre-Qualification |
06 May 2017 |
Price bid opening |
10 May 2017 |
Approval Dates
Workorder Date |
20 Jul 2017 |
NA |
05 Aug 2017 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Kanhangad Proj Dn AEE - 1 |
Date: 07/10/2022 |
Work has been completed | 100% Completed
work completed and commissioned ,FCC submitted..
Kanhangad Proj Dn AEE - 1 |
Date: 29/09/2022 |
Work has been completed | 100% Completed
work completed and commissioned ,FCC submitted..