| Project | Jal Jeevan Mission- Kasaragod District- RWSS to Enmakaje and adjoining Villages- Phase II - (Balance work) Shivagiri area Part III-Laying distribution and providing FHTCs -Pipe line work |
|---|---|
| Project Code | KGDJJM08202940P5 |
| Type | Package |
| Main Project | Jal Jeevan Mission- Kasaragod District- Enmakaje Grama Panchayath- ARWSS to Enmakaje and adjoining Villages- Phase II - Laying distribution System and providing FHTC |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Jal Jeevan Mission- Kasaragod District- RWSS to Enmakaje and adjoining Villages- Phase II - (Balance work) Shivagiri area Part III-Laying distribution and providing FHTCs -Pipe line work |
| Status | Completed |
| District | Kasaragod |
| Executing Office | Bovikkanam WSP Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 8620000 |
| TS Number | 24872/2023-26-2-1 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 22/11/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 21 Mar 2024 |
| Expected date of Completion | 30/01/2025 |
| TS Date | 25 Oct 2023 |
|---|---|
| Estimate Approval | 25 Oct 2023 |
| NIT Approval | 25 Oct 2023 |
| Tender Closing | 30 Oct 2023 |
| Technichal Pre-Qualification | 31 Oct 2023 |
| Price bid opening | 31 Oct 2023 |
| Workorder Date | 31 Oct 2023 |
|---|---|
| NA | 22 Oct 2023 |
| Bovikkanam WSP Sn AE |
| Date: 06/02/2026 |
Work has been completed | 100% Completed
Work completed on 05/05/2025.
| Bovikkanam WSP Sn AE |
| Date: 04/02/2026 |
Work in progress | 83% Completed
Work in progress.