JJM-2021-22 - Full coverage - (Part-1) - CWSS to Peringottukurissi and Kuthannur Pts. - Pipeline extension, Providing 3415 Nos. FHTCs in Peringottukurissi Pt., Supply, Erection & Commissioning of R/W & C/W Pumpsets and flow meters
Project |
JJM-2021-22 - Full coverage - (Part-1) - CWSS to Peringottukurissi and Kuthannur Pts. - Pipeline extension, Providing 3415 Nos. FHTCs in Peringottukurissi Pt., Supply, Erection & Commissioning of R/W & C/W Pumpsets and flow meters |
Project Code |
PKDJJM022212256P1 |
Type |
Package |
Main Project |
JJM-2021-22 - Full coverage - (Part-1) - CWSS to Peringottukurissi and Kuthannur Pts. - Pipeline extension, Providing 3415 Nos. FHTCs in Peringottukurissi Pt., Supply, Erection & Commissioning of R/W & C/W Pumpsets and flow meters
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-2021-22 - Full coverage - (Part-1) - CWSS to Peringottukurissi and Kuthannur Pts. - Pipeline extension, Providing 3415 Nos. FHTCs in Peringottukurissi Pt., Supply, Erection & Commissioning of R/W & C/W Pumpsets and flow meters |
Status |
On-going |
District |
Palakkad |
Executing Office |
Kuzhalmannam Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
50900000 |
TS Number |
TS/2022-2023/2022/10258 |
Technical specification |
Providing 3415 Nos. FHTCs in Peringottukurissi Pt., Supply, Erection & Commissioning of R/W & C/W Pumpsets and flow meters |
Contractor |
Dileep P (Mob: 9497072915) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
20/07/2022 |
Scheduled date of Completion as per agreement |
19 Jan 2023 |
Expected date of Completion |
30/11/2023 |
Processing Dates
TS Date |
12 May 2022 |
Estimate Approval |
20 Jul 2022 |
NIT Approval |
20 Jul 2022 |
Tender Closing |
05 Jul 2022 |
Technichal Pre-Qualification |
05 Jul 2022 |
Price bid opening |
07 Jul 2022 |
Approval Dates
Workorder Date |
20 Jul 2022 |
NA |
08 Aug 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Kuzhalmannam PH Sn AE |
Date: 12/01/2024 |
Work has been completed | 100% Completed
WORK COMPLETED ON 15.11.2023.
Kuzhalmannam PH Sn AE |
Date: 06/01/2024 |
Work in progress | 41% Completed
work in progress.