- Home
- State Plan 2021-22. Production and Trans...
State Plan 2021-22. Production and Transmission Improvements to MWSS to Panakkad Village in Malappuram Municipality. In Malappuram District.Laying of Raw water pumping main with 300 mm DI K9 pipe,Supply and Commission of 140 HP VT Pumpset.
Project |
State Plan 2021-22. Production and Transmission Improvements to MWSS to Panakkad Village in Malappuram Municipality. In Malappuram District.Laying of Raw water pumping main with 300 mm DI K9 pipe,Supply and Commission of 140 HP VT Pumpset. |
Project Code |
MLPGOK06218588 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
300 DI K9 pipe,140 HP VT Pumpset. |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram PH Dn |
AS Amount (Rs) |
20000000
|
AS Number |
KWA/JB/PIU-1/AE4/StatePlan/OPT/05/21-22 (VI) |
TS Amount (Rs) |
20000000 |
TS Number |
15732/2021-2022 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan 2021-22. Production and Transmission Improvements to MWSS to Panakkad Village in Malappuram Municipality. In Malappuram District.Laying of Raw water pumping main with 300 mm DI K9 pipe,Supply and Commission of 140 HP VT Pumpset. |
Malappuram Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
Recaste estimate re-submitted to SE re approval |
Malappuram PH Dn EE |
|
25 Mar 2024 |
Recaste estimate re-submitted to SE re approval |
Malappuram PH Dn EE |
|
21 Mar 2024 |
Recaste estimate re-submitted to SE re approval |
Malappuram PH Dn EE |
|
17 Feb 2024 |
Recaste estimate re-submitted to SE re approval |
Malappuram PH Dn EE |
|
14 Feb 2024 |
Recaste estimate re-submitted to SE re approval |
Malappuram PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
28/02/2023 |
Processing Dates
AS Date |
16 Jun 2021 |
TS Date |
20 Dec 2021 |