Jal Jeevan Mission 2021-22 ( Phase III) Augmentation of PRWSS . Providing FHTCs in Punnayurkulam Panchayath

Project Jal Jeevan Mission 2021-22 ( Phase III) Augmentation of PRWSS . Providing FHTCs in Punnayurkulam Panchayath
Project Code TCRJJM022213938
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission 2021-22 ( Phase III) Augmentation of PRWSS . Providing FHTCs in Punnayurkulam Panchayath
Status On-going
District Thrissur
Executing Office Thrissur PH Dn
AS Amount (Rs) 295000000
AS Number G.O.(Rt)No.134/2022/WRD Dated,Thiruvananthapuram, 23-02-2022
TS Amount (Rs) 222000000
TS Number TS/2022-2023/2022/20031
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 19287
Capacity in MLD 33.00
Actual Project Completion Date Date is not specified
Coverage Punnayurkulam Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission 2021-22 ( Phase III) Augmentation of PRWSS . Providing FHTCs in Punnayurkulam Panchayath Kunnamkulam Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Jun 2024 Work ongoing. PWD permission not received. At GP road work is ongoing .85%work completed. 1772 FHTCs. Kunnamkulam PH Sn - AE
24 Jun 2024 Work ongoing. PWD permission not received. At GP road work is ongoing .85%work completed. 1772 FHTCs. Kunnamkulam PH Sn - AE
22 Jun 2024 Work ongoing. PWD permission not received. At GP road work is ongoing .85%work completed. 1772 FHTCs. Kunnamkulam PH Sn - AE
21 Jun 2024 Work ongoing. PWD permission not received. At GP road work is ongoing .85%work completed. 1772 FHTCs. Thrissur PH Dn EE
20 Jun 2024 Work ongoing. PWD permission not received. At GP road work is ongoing .85%work completed. 1772 FHTCs. Kunnamkulam PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 05/12/2022
Scheduled date of Completion of the Project 04 Dec 2023
Expected date of Completion 30/06/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 05 Jul 2022

Other details

Project Officers View