Package III - Design, construction and commissioning of 55 MLD Water Treatment Plant, Clear water sump, supply and erection of clear water pump sets, 1000KVA Transformer and construction of substation building

Project Package III - Design, construction and commissioning of 55 MLD Water Treatment Plant, Clear water sump, supply and erection of clear water pump sets, 1000KVA Transformer and construction of substation building
Project Code KGDKIIFB0117579P2
Type Package
Main Project KIIFB-WSS TO KASARAGOD MUNICIPALITY AND CHEMMANAD PANCHAYATH - PHASE I
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB - WSS to Kasaragod Municipality and Chemmanad Panchayath - Phase I WTP-55 MLD Clear water Sump- 23LL CW Pump sets- 3 no.s( 1stby) 1000kva transformer -1 no.
Status On-going
District Kasaragod
Executing Office Project Division Kannur ( KGD)
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification WTP-55 MLD Clear water Sump- 23LL CW Pump sets- 3 no.s( 1stby) 1000kva transformer -1 no.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 06/11/2017
Scheduled date of Completion as per agreement 12 Apr 2019
Expected date of Completion 30/11/2021

Processing Dates

TS Date 03 Mar 2017
Estimate Approval 20 Mar 2017
NIT Approval 04 Apr 2017
Tender Closing 25 Apr 2017
Technichal Pre-Qualification 06 May 2017
Price bid opening 10 May 2017

Approval Dates

Workorder Date 13 Oct 2017
NA 04 Nov 2017

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kanhangad Proj Dn AEE - 1
Date: 07/10/2022

Work has been completed | 100% Completed

work completed and commissioned ,FCC submitted..

Kanhangad Proj Dn AEE - 1
Date: 29/09/2022

Work has been completed | 100% Completed

work completed and commissioned ,FCC submitted..