JJM-2021-22- Setting up / Up-gradation / operation of Laboratories for WQM &S- Procurement of 77 nos Hot Air Oven Natural Convection type for various Quality Control Laboratories of Kerala Water Authority

Project JJM-2021-22- Setting up / Up-gradation / operation of Laboratories for WQM &S- Procurement of 77 nos Hot Air Oven Natural Convection type for various Quality Control Laboratories of Kerala Water Authority
Project Code EKMJJM09218407P1
Type Package
Main Project JJM-2021-22- Setting up / Up-gradation / operation of Laboratories for WQM &S- Procurement of 77 nos Hot AIr Oven Natural Convection type for various Quality Control Laboratories of Kerala Water Authority
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Procurement of 77 nos Hot Air Oven Natural Convection type for various Quality Control Laboratories of Kerala Water Authority
Status On-going
District Ernakulam
Executing Office SRI Nettoor
Agreement Number
Agreement Date
TS Amount (Rs) 14738000
TS Number EST NO:2021/15616
Technical specification Procurement of 77 nos Hot Air Oven Natural Convection type for various Quality Control Laboratories of Kerala Water Authority

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/12/2021
Scheduled date of Completion as per agreement 08 Mar 2022
Expected date of Completion 08/03/2022

Processing Dates

TS Date 23 Oct 2021
Estimate Approval 23 Oct 2021
NIT Approval 28 Oct 2021
Tender Closing 19 Nov 2021
Technichal Pre-Qualification 13 Dec 2021
Price bid opening 17 Dec 2021

Approval Dates

Workorder Date 18 Dec 2021
NA 30 Dec 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nettoor SRI Circle Director
Date: 29/11/2022

Work in progress | 99% Completed

Installation completed. Awaiting reports from Regional EEs.

Nettoor SRI Circle Director
Date: 01/09/2022

Work in progress | 98% Completed

Installation completed. Awaiting reports from Regional EEs.