- Home
- DEPOSIT-Vazhathoppue GP-234/2023-24 - Re...
DEPOSIT-Vazhathoppue GP-234/2023-24 - Replacement of Old Distribution Lines at Various Locations of Gandhinagar Colony & New Pipe Line Extension at Gandhinagar Colony- Painav Division-General Civil Work
| Project |
DEPOSIT-Vazhathoppue GP-234/2023-24 - Replacement of Old Distribution Lines at Various Locations of Gandhinagar Colony & New Pipe Line Extension at Gandhinagar Colony- Painav Division-General Civil Work |
| Project Code |
IDKDEPO012517633 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
DEPOSIT-Vazhathoppue GP-234/2023-24 - Replacement of Old Distribution Lines at Various Locations of Gandhinagar Colony & New Pipe Line Extension at Gandhinagar Colony- Painav Division-General Civil Work |
| Status |
Completed |
| District |
Idukki |
| Executing Office |
Painavu Sn |
| AS Amount (Rs) |
282000
|
| AS Number |
134/25 |
| TS Amount (Rs) |
282000 |
| TS Number |
WRD/KWA-CE(CR)/EST_TS/11190/2022_5_11_10 |
| Total Bill Submitted (Rs) |
0 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
350 |
| Capacity in MLD |
5.00 |
| Actual Project Completion Date |
12 Dec 2025 |
| Coverage |
Various Locations of Gandhinagar Colony
|
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
DEPOSIT-Vazhathoppue GP-234/2023-24 Replacement of Old Distribution Lines at Various Locations of Gandhinagar Colony & New Pipe Line Extension at Gandhinagar Colony- Painav Division General Civil Work |
Painavu Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 22 Dec 2025 |
Work completed. |
Painavu PH Section AE |
|
| 10 Dec 2025 |
Laying of pipe completed, connection alteration in 25mm GI pipe ongoing |
Painavu PH Section AE |
|
| 05 Dec 2025 |
Laying of pipe completed, connection alteration in 25mm GI pipe ongoing |
Painavu PH Section AE |
|
| 02 Dec 2025 |
Laying of pipe completed, connection alteration in 25mm GI pipe ongoing |
Painavu PH Section AE |
|
| 24 Nov 2025 |
Laying of pipe completed, connection alteration in 25mm GI pipe ongoing |
Painavu PH Section AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
23/07/2025 |
| Scheduled date of Completion of the Project |
23 Aug 2025 |
| Expected date of Completion |
23/08/2025 |
Processing Dates
| AS Date |
23 Jan 2025 |
| TS Date |
25 Mar 2025 |