JJM - Kannur District- Chembilode Panchayath - WSS to Anjarakandy, Peralassery and adjoining Panchayaths Phase II

Project JJM - Kannur District- Chembilode Panchayath - WSS to Anjarakandy, Peralassery and adjoining Panchayaths Phase II
Project Code KNRJJM08202926
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing 5373 Nos FHTC in Chembilode Panchayath
Status On-going
District Kannur
Executing Office Kannur WS Dn
AS Amount (Rs) 121645000
AS Number G.O.(Rt)No.541/2020/WRD
TS Amount (Rs) 106319000
TS Number TS/2020-2021/2020/19150
Total Bill Submitted (Rs) 62543000
Total Bill Paid (Rs) 62543000
Population Benefitted 24000
Capacity in MLD 46.00
Actual Project Completion Date Date is not specified
Coverage Population Benefitted---24000
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Kannur District-Chembilode Pt-WSS to Anjarakandy and Adjoining Panchayaths (Balance work)-Laying distribution and Providing FHTCs-Pipeline Work. Perlassery Sn 2
2 JJM - Kannur District- Chembilode Panchayath - WSS to Anjarakandy, Peralassery and adjoining Panchayaths Phase II Perlassery Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Jun 2024 4142- Nos FHTCS provided. Physical progress 77%. Pipe supply, 29 Km laying and 4093 Nos FHTCS bill submitted-Remaining bill submitted.-Balance work arranged Perlassery Sn 2 AE
20 Jun 2024 4142- Nos FHTCS provided. Physical progress 77%. Pipe supply, 29 Km laying and 4093 Nos FHTCS bill submitted-Remaining bill submitted.-Balance work arranged Perlassery Sn 2 AE
10 Jun 2024 4142- Nos FHTCS provided. Physical progress 77%. Pipe supply, 29 Km laying and 4093 Nos FHTCS bill submitted-Remaining bill submitted.-Balance work arranged Perlassery Sn 2 AE
01 Jun 2024 4142- Nos FHTCS provided. Physical progress 77%. Pipe supply, 29 Km laying and 4093 Nos FHTCS bill submitted-Remaining bill submitted.-Balance work arranged Perlassery Sn 2 AE
22 May 2024 4142- Nos FHTCS provided. Physical progress 77%. Pipe supply, 29 Km laying and 4093 Nos FHTCS bill submitted-Remaining bill submitted.-Balance work arranged Perlassery Sn 2 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 06/11/2020
Scheduled date of Completion of the Project 04 May 2021
Expected date of Completion 31/03/2023

Processing Dates

AS Date 21 Aug 2020
TS Date 27 Aug 2020

Other details