JJM - Kannur District- Chembilode Panchayath - WSS to Anjarakandy, Peralassery and adjoining Panchayaths Phase II
Project |
JJM - Kannur District- Chembilode Panchayath - WSS to Anjarakandy, Peralassery and adjoining Panchayaths Phase II |
Project Code |
KNRJJM08202926 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Providing 5373 Nos FHTC in Chembilode Panchayath |
Status |
On-going |
District |
Kannur |
Executing Office |
Kannur WS Dn |
AS Amount (Rs) |
121645000
|
AS Number |
G.O.(Rt)No.541/2020/WRD |
TS Amount (Rs) |
106319000 |
TS Number |
TS/2020-2021/2020/19150 |
Total Bill Submitted (Rs) |
62543000 |
Total Bill Paid (Rs) |
62543000 |
Population Benefitted |
24000 |
Capacity in MLD |
46.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Population Benefitted---24000 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Kannur District-Chembilode Pt-WSS to Anjarakandy and Adjoining Panchayaths (Balance work)-Laying distribution and Providing FHTCs-Pipeline Work. |
Perlassery Sn 2 |
|
2 |
JJM - Kannur District- Chembilode Panchayath - WSS to Anjarakandy, Peralassery and adjoining Panchayaths Phase II |
Perlassery Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Jun 2024 |
4142- Nos FHTCS provided. Physical progress 77%. Pipe supply, 29 Km laying and 4093 Nos FHTCS bill submitted-Remaining bill submitted.-Balance work arranged |
Perlassery Sn 2 AE |
|
20 Jun 2024 |
4142- Nos FHTCS provided. Physical progress 77%. Pipe supply, 29 Km laying and 4093 Nos FHTCS bill submitted-Remaining bill submitted.-Balance work arranged |
Perlassery Sn 2 AE |
|
10 Jun 2024 |
4142- Nos FHTCS provided. Physical progress 77%. Pipe supply, 29 Km laying and 4093 Nos FHTCS bill submitted-Remaining bill submitted.-Balance work arranged |
Perlassery Sn 2 AE |
|
01 Jun 2024 |
4142- Nos FHTCS provided. Physical progress 77%. Pipe supply, 29 Km laying and 4093 Nos FHTCS bill submitted-Remaining bill submitted.-Balance work arranged |
Perlassery Sn 2 AE |
|
22 May 2024 |
4142- Nos FHTCS provided. Physical progress 77%. Pipe supply, 29 Km laying and 4093 Nos FHTCS bill submitted-Remaining bill submitted.-Balance work arranged |
Perlassery Sn 2 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
06/11/2020 |
Scheduled date of Completion of the Project |
04 May 2021 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
27 Aug 2020 |