| Project | PACKAGE VIII- CONSTRUCTION OF 5.25 LL CAPACITY OHSR AT PATTATHIKKUNNU , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN NEW MAHE GRAMA PANCHAYATH |
|---|---|
| Project Code | KNRJJM022213306P8 |
| Type | Package |
| Main Project | JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Construction of 5.25 LL capacity OHSR at Pattathikkunnu, demolishing the old OHSR , supplying ,laying and commissioning distribution system and providing FHTCs |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 322300000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/10644/2022_26_1_1 |
| Technical specification | Construction of 5.25 LL capacity OHSR at Pattathikkunnu, demolishing the old OHSR , supplying ,laying and commissioning distribution system and providing FHTCs |
| Contractor | STREFA PROJECTS PRIVATE LIMITED & KSAHMIRILAL CONSTRUCTIONS (P) LTD-JV (Mob: 9160012315) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 07/06/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 06 Jun 2024 |
| Expected date of Completion | 31/12/2025 |
| TS Date | 17 Nov 2022 |
|---|---|
| Estimate Approval | 17 Nov 2022 |
| NIT Approval | 17 Dec 2022 |
| Tender Closing | 27 Apr 2024 |
| Technichal Pre-Qualification | 27 Nov 2023 |
| Price bid opening | 29 Apr 2024 |
| Workorder Date | 08 May 2023 |
|---|---|
| NA | 05 Jun 2023 |
| Mattannur Project Sn 2 AE |
| Date: 22/04/2026 |
Work in progress | 61% Completed
Total distribution is 92.986 km.Pipe required is 87.982 km. in that 81.222 km Pipe has supplied. Pipe laying of 69.832km completed. House connection and HTC work is on going, 2014 nos. HTC completed. Total meter fixed is 2085 nos. construction of Temporary MS Tank completed and commissioned. Demolishing the old OHSR 100% completed . Railway line crossing by HDD method at peringadi railway crossing (28.5m) completed.carrier pipe of 200 mm MS pipe work completed. exit side connecting work also in progress. At Punnol(16.5m (PWD-NH) push through completed. Kidarankunnu(PWD-NH) started. Partial charging, line supply & interconnection at kidarankunnu completed.240nos HTC completed in to FHTC. Punnol in progress, LSGD Road restoration in progress, 15 km completed. PWD restoration 1.9 km tarring completed.617m GSB+WMM completed.in that 320m tarring completed.
| Mattannur Project Sn 2 AE |
| Date: 08/04/2026 |
Work in progress | 61% Completed
Total distribution is 92.986 km.Pipe required is 87.982 km. in that 81.222 km Pipe has supplied. Pipe laying of 69.832km completed. House connection and HTC work is on going, 2014 nos. HTC completed. Total meter fixed is 2085 nos. construction of Temporary MS Tank completed and commissioned. Demolishing the old OHSR 100% completed . Railway line crossing by HDD method at peringadi railway crossing (28.5m) completed.carrier pipe of 200 mm MS pipe work in progress,exit side connecting work also in progress. At Punnol(16.5m (PWD-NH) push through completed. Kidarankunnu(PWD-NH) started. Partial charging, line supply & interconnection at kidarankunnu completed.240nos HTC completed in to FHTC. Punnol in progress, LSGD Road restoration in progress, 15 km completed. PWD restoration 1.9 km tarring completed.617m GSB+WMM completed.in that 320m tarring completed.