PACKAGE VIII- CONSTRUCTION OF 5.25 LL CAPACITY OHSR AT PATTATHIKKUNNU , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN NEW MAHE GRAMA PANCHAYATH

Project PACKAGE VIII- CONSTRUCTION OF 5.25 LL CAPACITY OHSR AT PATTATHIKKUNNU , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN NEW MAHE GRAMA PANCHAYATH
Project Code KNRJJM022213306P8
Type Package
Main Project JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Construction of 5.25 LL capacity OHSR at Pattathikkunnu, demolishing the old OHSR , supplying ,laying and commissioning distribution system and providing FHTCs
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 322300000
TS Number WRD/KWA-CE(NR)/EST_TS/10644/2022_26_1_1
Technical specification Construction of 5.25 LL capacity OHSR at Pattathikkunnu, demolishing the old OHSR , supplying ,laying and commissioning distribution system and providing FHTCs
Contractor STREFA PROJECTS PRIVATE LIMITED & KSAHMIRILAL CONSTRUCTIONS (P) LTD-JV (Mob: 9160012315)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/06/2023
Scheduled date of Completion as per agreement 06 Jun 2024
Expected date of Completion 31/12/2025

Processing Dates

TS Date 17 Nov 2022
Estimate Approval 17 Nov 2022
NIT Approval 17 Dec 2022
Tender Closing 27 Apr 2024
Technichal Pre-Qualification 27 Nov 2023
Price bid opening 29 Apr 2024

Approval Dates

Workorder Date 08 May 2023
NA 05 Jun 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 22/04/2026

Work in progress | 61% Completed

Total distribution is 92.986 km.Pipe required is 87.982 km. in that 81.222 km Pipe has supplied. Pipe laying of 69.832km completed. House connection and HTC work is on going, 2014 nos. HTC completed. Total meter fixed is 2085 nos. construction of Temporary MS Tank completed and commissioned. Demolishing the old OHSR 100% completed . Railway line crossing by HDD method at peringadi railway crossing (28.5m) completed.carrier pipe of 200 mm MS pipe work completed. exit side connecting work also in progress. At Punnol(16.5m (PWD-NH) push through completed. Kidarankunnu(PWD-NH) started. Partial charging, line supply & interconnection at kidarankunnu completed.240nos HTC completed in to FHTC. Punnol in progress, LSGD Road restoration in progress, 15 km completed. PWD restoration 1.9 km tarring completed.617m GSB+WMM completed.in that 320m tarring completed.

Mattannur Project Sn 2 AE
Date: 08/04/2026

Work in progress | 61% Completed

Total distribution is 92.986 km.Pipe required is 87.982 km. in that 81.222 km Pipe has supplied. Pipe laying of 69.832km completed. House connection and HTC work is on going, 2014 nos. HTC completed. Total meter fixed is 2085 nos. construction of Temporary MS Tank completed and commissioned. Demolishing the old OHSR 100% completed . Railway line crossing by HDD method at peringadi railway crossing (28.5m) completed.carrier pipe of 200 mm MS pipe work in progress,exit side connecting work also in progress. At Punnol(16.5m (PWD-NH) push through completed. Kidarankunnu(PWD-NH) started. Partial charging, line supply & interconnection at kidarankunnu completed.240nos HTC completed in to FHTC. Punnol in progress, LSGD Road restoration in progress, 15 km completed. PWD restoration 1.9 km tarring completed.617m GSB+WMM completed.in that 320m tarring completed.