Project | KIIFB -WRD 002-11- WSS TO MATTANNUR & IRITTY MUNICIPALITIES-PACKAGE IV |
---|---|
Project Code | KNRKIIFB0117528P4 |
Type | Package |
Main Project | KIIFB -WRD 002-11 -WSS TO MATTANNUR AND IRITTY MUNICIPALITIES |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Construction of 15 LL Capacity O.H.S.R at Iritty H.S.S, Supplying & Laying Gravity Main from GLSR at Chavasseryparamba to Iritty H.S.S( 450 mm & 400 mm DI K9 13070m) ,Gravity branch main (200 mm DI K9 725m) , Interconnection work( 500 mm DI K9 450 m) ,Supplying & Laying Pumping Main to Manjakunnu (200 mm DI K9 2230m), Construction of 3L.L G.L.S.R at Manjakunnu . |
Status | Completed |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 209000000 |
TS Number | TS/2019-2020/2020/781 |
Technical specification | Construction of 15 LL capacity OHSR , Gravity main, Gravity branch main, Pumping main to Manjakkunnu , Construction of 3 LL GLSR at Manjakkunnu. |
Contractor | Thomas K Paul (Mob: 9447061604) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 05/11/2020 |
---|---|
Scheduled date of Completion as per agreement | 04 May 2022 |
Expected date of Completion | 15/01/2023 |
TS Date | 19 Jun 2017 |
---|---|
Estimate Approval | 20 Mar 2020 |
Tender Closing | 30 Jun 2020 |
Price bid opening | 20 Aug 2020 |
Workorder Date | 05 Nov 2020 |
---|---|
NA | 20 Nov 2020 |
Mattannur Project Sn 2 AE |
Date: 11/01/2024 |
Work has been completed | 100% Completed
Final bill submitted .
Mattannur Project Sn 2 AE |
Date: 03/03/2023 |
Work has been completed | 100% Completed
Completed.