JJM - Kasaragod District -Muliyar Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 1(Zone 1)-Laying Distribution system and providing FHTCs- from OHSR at Iriyenni.

Project JJM - Kasaragod District -Muliyar Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 1(Zone 1)-Laying Distribution system and providing FHTCs- from OHSR at Iriyenni.
Project Code KGDJJM072110789
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Muliyar Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 1(Zone 1)-Laying Distribution system and providing FHTCs- from OHSR at Iriyenn
Status On-going
District Kasaragod
Executing Office Kanhangad Project Division
AS Amount (Rs) 1272000000
AS Number G.O(Rt)No.489/2021/WRD
TS Amount (Rs) 117100000
TS Number TS/2021-2022/2021/40304
Total Bill Submitted (Rs) 13137093
Total Bill Paid (Rs)
Population Benefitted 25095
Capacity in MLD 0.03
Actual Project Completion Date 13 Aug 2022
Coverage coverage area muliyar

Packages

No. Project Name Location View
1 JJM - Kasaragod District -Muliyar Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 1(Zone 1)-Laying Distribution system and providing FHTCs- from OHSR at Iriyenni. Project Division Kannur ( KGD)

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 May 2024 pipe supplied is 30.437 kms and 26407 mtrs pvc pipe laid.Work in progress.Permission received from forest department on 04.10.2023(order no.KGG-1173/23) ..CC 3rd & part bill submitted.Time extension applied for 30.06.2024.HTC connection work in progress and 405 nos HTC are approved .Permission for road cutting placed before PWD vide ROW/1097232/107246 dated 22/02/2024 which is under process Kanhangad Proj Dn AE - 1
14 May 2024 pipe supplied is 30.437 kms and 26407 mtrs pvc pipe laid.Work in progress.Permission received from forest department on 04.10.2023(order no.KGG-1173/23) ..CC 3rd & part bill submitted.Time extension applied for 30.06.2024.HTC connection work in progress and 405 nos HTC are approved .Permission for road cutting placed before PWD vide ROW/1097232/107246 dated 22/02/2024 which is under process Kanhangad Proj Dn AE - 1
09 May 2024 pipe supplied is 30.437 kms and 26407 mtrs pvc pipe laid.Work in progress.Permission received from forest department on 04.10.2023(order no.KGG-1173/23) ..CC 3rd & part bill submitted.Time extension applied for 30.06.2024.HTC connection work in progress and 300 nos HTC are approved .Permission for road cutting placed before PWD vide ROW/1097232/107246 dated 22/02/2024 which is under process. Kanhangad Proj Dn AE - 1
03 May 2024 Work in progress.Permission received from forest department on 04.10.2023(order no.KGG-1173/23) .26.394 kms of pipeline laid.CC 2nd & part bill submitted.Time extension applied for 30.06.2024.HTC connection work in progress and 300 nos HTC are given.Permission for road cutting placed before PWD vide ROW/1097232/107246 dated 22/02/2024.The 3rd bill is under preparation Kanhangad Proj Dn AE - 1
23 Apr 2024 Work in progress.Permission received from forest department on 04.10.2023(order no.KGG-1173/23) .26.394 kms of pipeline laid.CC 2nd & part bill submitted.Time extension applied for 30.06.2024.HTC connection work in progress and 300 nos HTC are given.Permission for road cutting placed before PWD vide ROW/1097232/107246 dated 22/02/2024.The 3rd bill is under preparation Kanhangad Proj Dn AE - 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/03/2022
Scheduled date of Completion of the Project 13 Aug 2022
Expected date of Completion 30/11/2023

Processing Dates

AS Date 22 Jul 2021
TS Date 07 Dec 2021