JJM - Kasaragod District -Muliyar Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 1(Zone 1)-Laying Distribution system and providing FHTCs- from OHSR at Iriyenni.
Project |
JJM - Kasaragod District -Muliyar Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 1(Zone 1)-Laying Distribution system and providing FHTCs- from OHSR at Iriyenni. |
Project Code |
KGDJJM072110789 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Muliyar Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 1(Zone 1)-Laying Distribution system and providing FHTCs- from OHSR at Iriyenn |
Status |
On-going |
District |
Kasaragod |
Executing Office |
Kanhangad Project Division |
AS Amount (Rs) |
1272000000
|
AS Number |
G.O(Rt)No.489/2021/WRD |
TS Amount (Rs) |
117100000 |
TS Number |
TS/2021-2022/2021/40304 |
Total Bill Submitted (Rs) |
13137093 |
Total Bill Paid (Rs) |
|
Population Benefitted |
25095 |
Capacity in MLD |
0.03 |
Actual Project Completion Date |
13 Aug 2022 |
Coverage |
coverage area muliyar |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM - Kasaragod District -Muliyar Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 1(Zone 1)-Laying Distribution system and providing FHTCs- from OHSR at Iriyenni. |
Project Division Kannur ( KGD) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 May 2024 |
pipe supplied is 30.437 kms and 26407 mtrs pvc pipe laid.Work in progress.Permission received from forest department on 04.10.2023(order no.KGG-1173/23) ..CC 3rd & part bill submitted.Time extension applied for 30.06.2024.HTC connection work in progress and 405 nos HTC are approved .Permission for road cutting placed before PWD vide ROW/1097232/107246 dated 22/02/2024 which is under process |
Kanhangad Proj Dn AE - 1 |
|
14 May 2024 |
pipe supplied is 30.437 kms and 26407 mtrs pvc pipe laid.Work in progress.Permission received from forest department on 04.10.2023(order no.KGG-1173/23) ..CC 3rd & part bill submitted.Time extension applied for 30.06.2024.HTC connection work in progress and 405 nos HTC are approved .Permission for road cutting placed before PWD vide ROW/1097232/107246 dated 22/02/2024 which is under process |
Kanhangad Proj Dn AE - 1 |
|
09 May 2024 |
pipe supplied is 30.437 kms and 26407 mtrs pvc pipe laid.Work in progress.Permission received from forest department on 04.10.2023(order no.KGG-1173/23) ..CC 3rd & part bill submitted.Time extension applied for 30.06.2024.HTC connection work in progress and 300 nos HTC are approved .Permission for road cutting placed before PWD vide ROW/1097232/107246 dated 22/02/2024 which is under process. |
Kanhangad Proj Dn AE - 1 |
|
03 May 2024 |
Work in progress.Permission received from forest department on 04.10.2023(order no.KGG-1173/23) .26.394 kms of pipeline laid.CC 2nd & part bill submitted.Time extension applied for 30.06.2024.HTC connection work in progress and 300 nos HTC are given.Permission for road cutting placed before PWD vide ROW/1097232/107246 dated 22/02/2024.The 3rd bill is under preparation |
Kanhangad Proj Dn AE - 1 |
|
23 Apr 2024 |
Work in progress.Permission received from forest department on 04.10.2023(order no.KGG-1173/23) .26.394 kms of pipeline laid.CC 2nd & part bill submitted.Time extension applied for 30.06.2024.HTC connection work in progress and 300 nos HTC are given.Permission for road cutting placed before PWD vide ROW/1097232/107246 dated 22/02/2024.The 3rd bill is under preparation |
Kanhangad Proj Dn AE - 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
03/03/2022 |
Scheduled date of Completion of the Project |
13 Aug 2022 |
Expected date of Completion |
30/11/2023 |
Processing Dates
AS Date |
22 Jul 2021 |
TS Date |
07 Dec 2021 |