Project | JJM - AUGMENTATION OF WATER SUPPLY SCHEME TO KOTAMKKARA PANCHAYATH - ESTIMATE FOR NEW WATER CONNECTION ( 5850 FHTCs) |
---|---|
Project Code | KLMJJM08207437P1 |
Type | Package |
Main Project | JJM - AUGMENTATION OF WATER SUPPLY SCHEME TO KOTAMKKARA PANCHAYATH - ESTIMATE FOR NEW WATER CONNECTION ( 5850 FHTCs) |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM - AUGMENTATION OF WATER SUPPLY SCHEME TO KOTAMKKARA PANCHAYATH - ESTIMATE FOR NEW WATER CONNECTION ( 5850 FHTCs) |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 80900000 |
TS Number | TS/2020-2021/2020/1319 |
Technical specification | Providing FHTCs - 5850nunbers |
Contractor | M/s HITECH CONSTRUCTION GROUP (Mob: 9656737227) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 21/06/2021 |
---|---|
Scheduled date of Completion as per agreement | 14 Apr 2022 |
Expected date of Completion | 20/06/2022 |
TS Date | 25 Jan 2021 |
---|---|
Estimate Approval | 25 Jan 2021 |
NIT Approval | 29 Jan 2021 |
Tender Closing | 22 Feb 2021 |
Technichal Pre-Qualification | 24 Feb 2021 |
Price bid opening | 25 Feb 2021 |
Workorder Date | 26 Feb 2021 |
---|---|
NA | 15 Apr 2021 |
Kollam Project HD |
Date: 16/10/2022 |
Work has been completed | 100% Completed
Work completed by providing 3585 connections out of total 5850 nos by providing fhtc in available existing main line distribution system. Balance connections shall be arranged in phase 3 after completing the laying of new main lines.
Kollam Project HD |
Date: 15/10/2022 |
Work in progress | 60% Completed
Work closing request submitted by Contractor. Total number of connections provided is 3585nos. Final bill submitted.