- Home
- JJM -202-21- Retrofitting/Augmentation o...
JJM -202-21- Retrofitting/Augmentation of UWSS to Anakkayam - Providing FHTCs, replacing 350 mm AC and 355 mm PVC pipes, replacing filter bed with dual media, supply and erection of centrifugal pumps
Project |
JJM -202-21- Retrofitting/Augmentation of UWSS to Anakkayam - Providing FHTCs, replacing 350 mm AC and 355 mm PVC pipes, replacing filter bed with dual media, supply and erection of centrifugal pumps |
Project Code |
MLPJJM08204586P1 |
Type |
Package |
Main Project |
JJM -2020-21- Retrofitting/Augmentation of UWSS to Anakkayam - Providing FHTCs, replacing 350 mm AC and 355 mm PVC pipes, replacing filter bed with dual media, supply and erection of centrifugal pumps
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
FHTCS,Pipe line extension,
,WTP works, pump sets, filter media
|
Status |
On-going |
District |
Malappuram |
Executing Office |
Manjeri PH Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
251000000 |
TS Number |
Reg .No. 6670/ 2020-2021 dt. 28.08.20 |
Technical specification |
JJM Retrofitting/Augmentation of UWSS to Anakkayam - Providing FHTCs, replacing 350 mm AC and 355 mm PVC pipes, replacing filter bed with dual media, supply and erection of centrifugal pumps
|
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
03 Jan 2022 |
Pending |
Pending |
Road Cut Related Risk |
Road cutting permission from PWD for Anakkayam Irumbuzhi road not obtained. PWD informed that this is under the DLP of ULCCS but can be given by Feb. But not obtained. Issue raised in 3 DICC meetings. |
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
02/10/2020 |
Scheduled date of Completion as per agreement |
05 Aug 2021 |
Expected date of Completion |
30/11/2022 |
Processing Dates
TS Date |
28 Aug 2020 |
Estimate Approval |
21 Aug 2020 |
NIT Approval |
31 Aug 2020 |
Tender Closing |
31 Aug 2020 |
Technichal Pre-Qualification |
25 Sep 2020 |
Price bid opening |
26 Sep 2020 |
Approval Dates
Workorder Date |
16 Oct 2020 |
NA |
06 Nov 2020 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Manjeri AE |
Date: 26/06/2024 |
Work in progress | 87% Completed
693m 150mm DI and 257m 250mm DI laid on manjeri - malappuram road from anakkayam to muttipalam.
Manjeri AE |
Date: 11/06/2024 |
Work in progress | 87% Completed
693m 150mm DI and 257m 250mm DI laid on manjeri - malappuram road from anakkayam to muttipalam.
.