JJM -202-21- Retrofitting/Augmentation of UWSS to Anakkayam - Providing FHTCs, replacing 350 mm AC and 355 mm PVC pipes, replacing filter bed with dual media, supply and erection of centrifugal pumps

Project JJM -202-21- Retrofitting/Augmentation of UWSS to Anakkayam - Providing FHTCs, replacing 350 mm AC and 355 mm PVC pipes, replacing filter bed with dual media, supply and erection of centrifugal pumps
Project Code MLPJJM08204586P1
Type Package
Main Project JJM -2020-21- Retrofitting/Augmentation of UWSS to Anakkayam - Providing FHTCs, replacing 350 mm AC and 355 mm PVC pipes, replacing filter bed with dual media, supply and erection of centrifugal pumps
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description FHTCS,Pipe line extension, ,WTP works, pump sets, filter media
Status On-going
District Malappuram
Executing Office Manjeri PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 251000000
TS Number Reg .No. 6670/ 2020-2021 dt. 28.08.20
Technical specification JJM Retrofitting/Augmentation of UWSS to Anakkayam - Providing FHTCs, replacing 350 mm AC and 355 mm PVC pipes, replacing filter bed with dual media, supply and erection of centrifugal pumps

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
03 Jan 2022 Pending Pending Road Cut Related Risk Road cutting permission from PWD for Anakkayam Irumbuzhi road not obtained. PWD informed that this is under the DLP of ULCCS but can be given by Feb. But not obtained. Issue raised in 3 DICC meetings. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 02/10/2020
Scheduled date of Completion as per agreement 05 Aug 2021
Expected date of Completion 30/11/2022

Processing Dates

TS Date 28 Aug 2020
Estimate Approval 21 Aug 2020
NIT Approval 31 Aug 2020
Tender Closing 31 Aug 2020
Technichal Pre-Qualification 25 Sep 2020
Price bid opening 26 Sep 2020

Approval Dates

Workorder Date 16 Oct 2020
NA 06 Nov 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Manjeri AE
Date: 26/06/2024

Work in progress | 87% Completed

693m 150mm DI and 257m 250mm DI laid on manjeri - malappuram road from anakkayam to muttipalam.

Manjeri AE
Date: 11/06/2024

Work in progress | 87% Completed

693m 150mm DI and 257m 250mm DI laid on manjeri - malappuram road from anakkayam to muttipalam. .