JJM- Providing FHTC to households in Erattayar Panchayat
Project |
JJM- Providing FHTC to households in Erattayar Panchayat |
Project Code |
IDKJJM08203350 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM- Providing FHTC to households in Erattayar Panchayat from existing and ongoing scheme |
Status |
On-going |
District |
Idukki |
Executing Office |
Kattappana Project Dn |
AS Amount (Rs) |
28495000
|
AS Number |
G.O(Rt)No.541/2020/WRD |
TS Amount (Rs) |
28380000 |
TS Number |
TS/2020-2021/2020/18550 Dated: 27-08-2020,TS/2020-2021/2020/17155 Dated: 03-09-2020 |
Total Bill Submitted (Rs) |
23859070 |
Total Bill Paid (Rs) |
23859070 |
Population Benefitted |
17727 |
Capacity in MLD |
2.00 |
Actual Project Completion Date |
14 Apr 2021 |
Coverage |
Erattayar Panchayat |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Package II- JJM -Erattayar- Providing FHTCs from existing and ongoing Scheme - Circle Tender |
Project Division Kattapana |
|
2 |
Package I- JJM-Erattayar- Providing FHTC from Existing Scheme- Division Tender |
Project Division Kattapana |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
06 Mar 2024 |
Package 1 completed , package 2- 85 % completed . More connections can only be provided after JJM Erattayar scheme |
Kattappana AEE 1 |
|
05 Mar 2024 |
Package 1 completed , package 2- 85 % completed . More connections can only be provided after JJM Erattayar scheme |
Kattappana AEE 1 |
|
04 Mar 2024 |
Package 1 completed , package 2- 85 % completed . More connections can only be provided after JJM Erattayar scheme |
Kattappana AEE 1 |
|
03 Mar 2024 |
Package 1 completed , package 2- 85 % completed . More connections can only be provided after JJM Erattayar scheme |
Kattappana AEE 1 |
|
02 Mar 2024 |
Package 1 completed , package 2- 85 % completed . More connections can only be provided after JJM Erattayar scheme |
Kattappana AEE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
27/08/2020 |
Scheduled date of Completion of the Project |
14 Apr 2021 |
Expected date of Completion |
13/10/2021 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
27 Aug 2020 |