- Home
- AMRUT 2.0 - Pipe line extension and Prov...
AMRUT 2.0 - Pipe line extension and Providing house hold connections in Chengannur Municipality.-AMRUT 2.0 - Pipe line extension and Providing house hold connections in Chengannur Municipality.
Project |
AMRUT 2.0 - Pipe line extension and Providing house hold connections in Chengannur Municipality.-AMRUT 2.0 - Pipe line extension and Providing house hold connections in Chengannur Municipality. |
Project Code |
ALPAMRUT112213369 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT 2.0 - Pipe line extension and Providing house hold connections in Chengannur Municipality.-AMRUT 2.0 - Pipe line extension and Providing house hold connections in Chengannur Municipality. |
Status |
On-going |
District |
Alappuzha |
Executing Office |
Alappuzha PH Dn |
AS Amount (Rs) |
33500000
|
AS Number |
GO(Rt)No.2906/2022/LSGD |
TS Amount (Rs) |
33400000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/6197/2022_26_1_1 |
Total Bill Submitted (Rs) |
5719701 |
Total Bill Paid (Rs) |
2539412 |
Population Benefitted |
16530 |
Capacity in MLD |
4.50 |
Actual Project Completion Date |
02 Aug 2024 |
Coverage |
Chengannur Muncipality |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2.0 - Pipe line extension and Providing house hold connections in Chengannur Municipality.-AMRUT 2.0 - Pipe line extension and Providing house hold connections in Chengannur Municipality. |
Chengannur WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 May 2024 |
90 mm PVC Pipe (10 kg) - 2393m / 2500m, 110 mm PVC Pipe (10 kg) - 1500m / 1500m laying work completed. 160 mm PVC 600m /600m Supplied. Road Cutting Permission to be obtained for laying. Fund Request for Restoration BG submitted. GI Pipes supplied. 80 mm GI Laying in progress -920m/1200m. Providing FHTCs in progress - 157/400 |
Chengannur PH Sn AE |
|
13 May 2024 |
90 mm PVC Pipe (10 kg) - 2393m / 2500m, 110 mm PVC Pipe (10 kg) - 1500m / 1500m laying work completed. 160 mm PVC 600m /600m Supplied. Road Cutting Permission to be obtained for laying. Fund Request for Restoration BG submitted. GI Pipes supplied. 80 mm GI Laying in progress -890m/1200m. Providing FHTCs in progress - 154/400 |
Chengannur PH Sn AE |
|
09 May 2024 |
90 mm PVC Pipe (10 kg) - 2393m / 2500m, 110 mm PVC Pipe (10 kg) - 1500m / 1500m laying work completed. 160 mm PVC 600m /600m Supplied. Road Cutting Permission to be obtained for laying. Fund Request for Restoration BG submitted. GI Pipes supplied. 80 mm GI Laying in progress -820m/1200m. Providing FHTCs in progress - 148/400 |
Chengannur PH Sn AE |
|
06 May 2024 |
90 mm PVC Pipe (10 kg) - 2393m / 2500m, 110 mm PVC Pipe (10 kg) - 1500m / 1500m laying work completed. 160 mm PVC 600m /600m Supplied. Road Cutting Permission to be obtained for laying. Fund Request for Restoration BG submitted. GI Pipes supplied. 80 mm GI Laying in progress -750m/1200m. Providing FHTCs in progress - 142/400 |
Chengannur PH Sn AE |
|
02 May 2024 |
90 mm PVC Pipe (10 kg) - 2393m / 2500m, 110 mm PVC Pipe (10 kg) - 1500m / 1500m laying work completed. 160 mm PVC 600m /600m Supplied. Road Cutting Permission to be obtained for laying. Fund Request for Restoration BG submitted. GI Pipes supplied. 80 mm GI Laying in progress -680m/1200m. Providing FHTCs in progress - 135/400 |
Chengannur PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
03/08/2023 |
Scheduled date of Completion of the Project |
02 Aug 2024 |
Expected date of Completion |
02/08/2024 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
14 Mar 2023 |