- Home
- State Plan 2024-25-CWSS to Chithara and...
State Plan 2024-25-CWSS to Chithara and adj Pts - Removal of sand and silt near leading channel at kulathupuzha river near Mylamoodu
| Project |
State Plan 2024-25-CWSS to Chithara and adj Pts - Removal of sand and silt near leading channel at kulathupuzha river near Mylamoodu |
| Project Code |
KLMGOK072416380 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
DRW |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
Removal of sand and silt near leading channel at kulathupuzha river-at Mylamoodu |
| Status |
Completed |
| District |
Kollam |
| Executing Office |
Kadakkal PH Sub Dn |
| AS Amount (Rs) |
496000
|
| AS Number |
PIU1/SP/09/2024-25 |
| TS Amount (Rs) |
494700 |
| TS Number |
10160/2024-2025 |
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
31 Mar 2025 |
| Coverage |
|
Packages
| No. |
Project Name |
Location |
View |
| 1 |
State Plan 2024-25-CWSS to Chithara and adj Pts - Removal of sand and silt near leading channel at kulathupuzha river near Mylamoodu |
Madathara Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 01 Sep 2025 |
Work completed |
Kadakkal PH Sub Dn - AEE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
Date is not specified |
| Scheduled date of Completion of the Project |
Date is not specified |
| Expected date of Completion |
Date is not specified |
Processing Dates
| AS Date |
25 Jul 2024 |
| TS Date |
08 Aug 2024 |