Jal Jeevan Mission (JJM)-3rd SLSSC - CWSS to Pallickal Panchayath-Laying distribution system & providing 4991FHTCs in Zone-3 (from Pazhakulam pass junction OH Tank)
Project |
Jal Jeevan Mission (JJM)-3rd SLSSC - CWSS to Pallickal Panchayath-Laying distribution system & providing 4991FHTCs in Zone-3 (from Pazhakulam pass junction OH Tank) |
Project Code |
PTAJJM092115051 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-3rd SLSSC - CWSS to Pallickal Panchayath-Laying distribution system & providing 4991FHTCs in Zone-3 (from Pazhakulam pass junction OH Tank) |
Status |
On-going |
District |
Pathanamthitta |
Executing Office |
Pathanamthitta PH Dn |
AS Amount (Rs) |
992600000
|
AS Number |
Go(Rt) NO.489/2021/WRD |
TS Amount (Rs) |
395300000 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/3884/2023_12_1_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-3rd SLSSC - CWSS to Pallickal Panchayath-Laying distribution system & providing 4991FHTCs in Zone-3 (from Pazhakulam pass junction OH Tank) |
Pathanamthitta PH Dn |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
05/07/2023 |
Scheduled date of Completion of the Project |
06 Jun 2024 |
Expected date of Completion |
06/06/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
22 Mar 2023 |