Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (3042nos) in Nellaya Grama Panchayath- Phase II

Project JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (3042nos) in Nellaya Grama Panchayath- Phase II
Project Code PKDJJM09219392P1
Type Package
Main Project JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (3042nos) in Nellaya Grama Panchayath- Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (3042nos) in Nellaya Grama Panchayath- Phase II
Status On-going
District Palakkad
Executing Office Pattambi PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 82300000
TS Number TS/2021-2022/2020/27412
Technical specification 3042nos
Contractor LUKMAN THAMARASSERI (Mob: 7025150000)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/02/2022
Scheduled date of Completion as per agreement 09 Aug 2022
Expected date of Completion 31/01/2024

Processing Dates

TS Date 26 Nov 2021
Estimate Approval 26 Nov 2021
Tender Closing 23 Nov 2021
Price bid opening 26 Nov 2021

Approval Dates

Workorder Date 10 Feb 2022
NA 16 Mar 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Pattambi PH Sn AE
Date: 26/06/2024

Work in progress | 99% Completed

HDPE pipe laying completed. 80mm GI pipe laying completed, 3042 connection provided (350 no HTC ) , chlorinator & tonners are supplied , 300mm DI pipe 2020m stored at site.300mm DI PIPE WORK NOT STARTED ,Beacause of road cutting issues from panchayath .

Pattambi PH Sn AE
Date: 22/06/2024

Work in progress | 99% Completed

HDPE pipe laying completed. 80mm GI pipe laying completed, 3042 connection provided (350 no HTC ) , chlorinator & tonners are supplied , 300mm DI pipe 2020m stored at site.300mm DI PIPE WORK NOT STARTED ,Beacause of road cutting issues from panchayath .