Project | JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (3042nos) in Nellaya Grama Panchayath- Phase II |
---|---|
Project Code | PKDJJM09219392P1 |
Type | Package |
Main Project | JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (3042nos) in Nellaya Grama Panchayath- Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (3042nos) in Nellaya Grama Panchayath- Phase II |
Status | On-going |
District | Palakkad |
Executing Office | Pattambi PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 82300000 |
TS Number | TS/2021-2022/2020/27412 |
Technical specification | 3042nos |
Contractor | LUKMAN THAMARASSERI (Mob: 7025150000) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 10/02/2022 |
---|---|
Scheduled date of Completion as per agreement | 09 Aug 2022 |
Expected date of Completion | 31/01/2024 |
TS Date | 26 Nov 2021 |
---|---|
Estimate Approval | 26 Nov 2021 |
Tender Closing | 23 Nov 2021 |
Price bid opening | 26 Nov 2021 |
Workorder Date | 10 Feb 2022 |
---|---|
NA | 16 Mar 2022 |
Pattambi PH Sn AE |
Date: 26/06/2024 |
Work in progress | 99% Completed
HDPE pipe laying completed. 80mm GI pipe laying completed, 3042 connection provided (350 no HTC ) , chlorinator & tonners are supplied , 300mm DI pipe 2020m stored at site.300mm DI PIPE WORK NOT STARTED ,Beacause of road cutting issues from panchayath .
Pattambi PH Sn AE |
Date: 22/06/2024 |
Work in progress | 99% Completed
HDPE pipe laying completed. 80mm GI pipe laying completed, 3042 connection provided (350 no HTC ) , chlorinator & tonners are supplied , 300mm DI pipe 2020m stored at site.300mm DI PIPE WORK NOT STARTED ,Beacause of road cutting issues from panchayath .