RKI-2019-20-WSS to Erumeli Panchayat- laying distribution system in Zone I(Part), Zone III(Part), Zone V(Par

Project RKI-2019-20-WSS to Erumeli Panchayat- laying distribution system in Zone I(Part), Zone III(Part), Zone V(Par
Project Code KTMRKI11192410
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description Supply and laying 15.9km distribution extension to Zone 1,3 & 5 to the uncovered areas of previously arranged works under NABARD & State plan. Work includes laying of 200 - 250mm DI K9 , 160mm to 90mm PVC pipes , 150mm to 80mm GI pipes & Providing 600 Nos House connections
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
AS Amount (Rs) 55000000
AS Number GO (Rt)123/2020 P&EA Dtd 3.3.2020
TS Amount (Rs) 48300000
TS Number TS/2020-2021/2019/6876 Dated: 07-07-2020
Total Bill Submitted (Rs) 29655700
Total Bill Paid (Rs) 29655700
Population Benefitted 10000
Capacity in MLD 10.00
Actual Project Completion Date 31 Aug 2022
Coverage Erumeli panchayat- ZoneI(part), Zone III(Part), Zone V(Part)
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 RKI-2019-20-WSS to Erumeli Panchayat- laying distribution system in Zone I(Part), Zone III(Part), Zone V(Part) Kottayam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Nov 2023 Laying completed 15km / 15.9km except 865m through NH 183 and interconnections works. Charging and commissioning of Zone III & V Part of the project completed with 6 km and 160 connections in Amakkunnu area. Lines to pakkanam area can be charged only after completing the pipelines through NH under this work (865m ) and under NABARD work (2.5 KM). MoRTH rejected applications for both works in RKI and NABARD several times . Demand note for licenfee and BG for the 865m in RKI received from NH and given to HO for fund ( Licence fee Rs 50016/- BG for Rs.97000/-). But the application for NABARD not yet considered as the same contain pipelines above 300mm . Part bill submitted up to the laying of 20/03/2021. Further progress will be only after getting the NH sanction. Kottayam Project Dn AE1
01 Feb 2023 Laying completed 15km / 15.9km except 865m through NH 183 and interconnections works. Charging and commissioning of Zone III & V Part of the project completed with 6 km and 160 connections in Amakkunnu area. Lines to pakkanam area can be charged only after completing the pipelines through NH under this work (865m ) and under NABARD work (2.5 KM). MoRTH rejected applications for both works in RKI and NABARD. Given the application again through ROW portal vide application no. ROW/1021236/25943 (ch.107/166 to 108/041 along NH 183 A) as per the direction in MD's review. The same again rejected saying the cutting application through NH be applied through MoRTH only which was already done. Part bill submitted up to the laying of 20/03/2021. Further progress will be only after getting the NH sanction. Kottayam Project Dn EE
04 Dec 2022 Laying completed 15km / 15.9km except 865m through NH 183 and interconnections works. Charging and commissioning of Zone III & V Part of the project completed with 6 km and 160 connections in Amakkunnu area. Lines to pakkanam area can be charged only after completing the pipelines through NH under this work (865m ) and under NABARD work (2.5 KM). MoRTH rejected applications for both works in RKI and NABARD. Given the application again through ROW portal vide application no. ROW/1021236/25943 (ch.107/166 to 108/041 along NH 183 A) as per the direction in MD's review. The same again rejected saying the cutting application through NH be applied through MoRTH only which was already done. Part bill submitted up to the laying of 20/03/2021. Further progress will be only after getting the NH sanction. Kottayam AE 3
06 Jul 2022 Laying completed 15km / 15.9km except 865m through NH 183 and interconnections works. Charging and commissioning of Zone III & V Part of the project completed with 6 km and 160 connections in Amakkunnu area. Lines to pakkanam area can be charged only after completing the pipelines through NH under this work (865m ) and under NABARD work (2.5 KM). MoRTH rejected applications for both works in RKI and NABARD. Given the application again through ROW portal vide application no. ROW/1021236/25943 (ch.107/166 to 108/041 along NH 183 A) as per the direction in MD's review. The same again rejected saying the cutting application through NH be applied through MoRTH only which was already done. Part bill submitted up to the laying of 20/03/2021. Further progress will be only after getting the NH sanction. Kottayam AE 3
30 Jun 2022 Laying completed 15km / 15.9km except 865m through NH 183 and interconnections works. Charging and commissioning of Zone III & V Part of the project completed with 6 km and 160 connections in Amakkunnu area. Lines to pakkanam area can be charged only after completing the pipelines through NH under this work (865m ) and under NABARD work (2.5 KM). MoRTH rejected applications for both works in RKI and NABARD. Given the application again through ROW portal vide application no. ROW/1021236/25943 (ch.107/166 to 108/041 along NH 183 A) as per the direction in MD's review. The same again rejected saying the cutting application through NH be applied through MoRTH only which was already done. Part bill submitted up to the laying of 20/03/2021. Further progress will be only after getting the NH sanction. Kottayam AE 3

Project Review

See All Review messages
Review Date Review Message Review Attended By
27 Oct 2021 All Road Cutting permissions from PWD are recieved and work started. It shall facilitate the partial commissioning of the scheme. For full commissioning 865 mtr of NH cutting is required for which application with all requirements of MorTH circular 2026 is submitted to RO/MorTH by EE/NH/Moovattuouzha on 25.10.2021. AEE
12 Feb 2021 Road cutting permission is to obtained for 26 locations. list and report attached AEE

Duration & Sanction dates

Date of start of Project 09/11/2020
Scheduled date of Completion of the Project 31 Jul 2021
Expected date of Completion 31/03/2024

Processing Dates

AS Date 03 Mar 2020
TS Date 07 Jul 2020

Other details

Project Officers View