RKI-2019-20-WSS to Erumeli Panchayat- laying distribution system in Zone I(Part), Zone III(Part), Zone V(Par
Project |
RKI-2019-20-WSS to Erumeli Panchayat- laying distribution system in Zone I(Part), Zone III(Part), Zone V(Par |
Project Code |
KTMRKI11192410 |
Type |
Main project |
Funding Agency |
RKI |
Category |
RKI |
Type of scheme |
Water Supply |
Scheme |
5475-00-115-94-05 |
Description |
Supply and laying 15.9km distribution extension to Zone 1,3 & 5 to the uncovered areas of previously arranged works under NABARD & State plan.
Work includes laying of 200 - 250mm DI K9 , 160mm to 90mm PVC pipes , 150mm to 80mm GI pipes & Providing 600 Nos House connections |
Status |
On-going |
District |
Kottayam |
Executing Office |
Kottayam Project Dn |
AS Amount (Rs) |
55000000
|
AS Number |
GO (Rt)123/2020 P&EA Dtd 3.3.2020 |
TS Amount (Rs) |
48300000 |
TS Number |
TS/2020-2021/2019/6876 Dated: 07-07-2020 |
Total Bill Submitted (Rs) |
29655700 |
Total Bill Paid (Rs) |
29655700 |
Population Benefitted |
10000 |
Capacity in MLD |
10.00 |
Actual Project Completion Date |
31 Aug 2022 |
Coverage |
Erumeli panchayat- ZoneI(part), Zone III(Part), Zone V(Part) |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
RKI-2019-20-WSS to Erumeli Panchayat- laying distribution system in Zone I(Part), Zone III(Part), Zone V(Part) |
Kottayam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Nov 2023 |
Laying completed 15km / 15.9km except 865m through NH 183 and interconnections works. Charging and commissioning of Zone III & V Part of the project completed with 6 km and 160 connections in Amakkunnu area. Lines to pakkanam area can be charged only after completing the pipelines through NH under this work (865m ) and under NABARD work (2.5 KM). MoRTH rejected applications for both works in RKI and NABARD several times . Demand note for licenfee and BG for the 865m in RKI received from NH and given to HO for fund ( Licence fee Rs 50016/- BG for Rs.97000/-). But the application for NABARD not yet considered as the same contain pipelines above 300mm . Part bill submitted up to the laying of 20/03/2021. Further progress will be only after getting the NH sanction. |
Kottayam Project Dn AE1 |
|
01 Feb 2023 |
Laying completed 15km / 15.9km except 865m through NH 183 and interconnections works. Charging and commissioning of Zone III & V Part of the project completed with 6 km and 160 connections in Amakkunnu area. Lines to pakkanam area can be charged only after completing the pipelines through NH under this work (865m ) and under NABARD work (2.5 KM). MoRTH rejected applications for both works in RKI and NABARD. Given the application again through ROW portal vide application no. ROW/1021236/25943 (ch.107/166 to 108/041 along NH 183 A) as per the direction in MD's review. The same again rejected saying the cutting application through NH be applied through MoRTH only which was already done. Part bill submitted up to the laying of 20/03/2021. Further progress will be only after getting the NH sanction. |
Kottayam Project Dn EE |
|
04 Dec 2022 |
Laying completed 15km / 15.9km except 865m through NH 183 and interconnections works. Charging and commissioning of Zone III & V Part of the project completed with 6 km and 160 connections in Amakkunnu area. Lines to pakkanam area can be charged only after completing the pipelines through NH under this work (865m ) and under NABARD work (2.5 KM). MoRTH rejected applications for both works in RKI and NABARD. Given the application again through ROW portal vide application no. ROW/1021236/25943 (ch.107/166 to 108/041 along NH 183 A) as per the direction in MD's review. The same again rejected saying the cutting application through NH be applied through MoRTH only which was already done. Part bill submitted up to the laying of 20/03/2021. Further progress will be only after getting the NH sanction. |
Kottayam AE 3 |
|
06 Jul 2022 |
Laying completed 15km / 15.9km except 865m through NH 183 and interconnections works. Charging and commissioning of Zone III & V Part of the project completed with 6 km and 160 connections in Amakkunnu area. Lines to pakkanam area can be charged only after completing the pipelines through NH under this work (865m ) and under NABARD work (2.5 KM). MoRTH rejected applications for both works in RKI and NABARD. Given the application again through ROW portal vide application no. ROW/1021236/25943 (ch.107/166 to 108/041 along NH 183 A) as per the direction in MD's review. The same again rejected saying the cutting application through NH be applied through MoRTH only which was already done. Part bill submitted up to the laying of 20/03/2021. Further progress will be only after getting the NH sanction. |
Kottayam AE 3 |
|
30 Jun 2022 |
Laying completed 15km / 15.9km except 865m through NH 183 and interconnections works. Charging and commissioning of Zone III & V Part of the project completed with 6 km and 160 connections in Amakkunnu area. Lines to pakkanam area can be charged only after completing the pipelines through NH under this work (865m ) and under NABARD work (2.5 KM). MoRTH rejected applications for both works in RKI and NABARD. Given the application again through ROW portal vide application no. ROW/1021236/25943 (ch.107/166 to 108/041 along NH 183 A) as per the direction in MD's review. The same again rejected saying the cutting application through NH be applied through MoRTH only which was already done. Part bill submitted up to the laying of 20/03/2021. Further progress will be only after getting the NH sanction. |
Kottayam AE 3 |
|
Review Date |
Review Message |
Review Attended By |
27 Oct 2021 |
All Road Cutting permissions from PWD are recieved and work started. It shall facilitate the partial commissioning of the scheme.
For full commissioning 865 mtr of NH cutting is required for which application with all requirements of MorTH circular 2026 is submitted to RO/MorTH by EE/NH/Moovattuouzha on 25.10.2021. |
AEE |
12 Feb 2021 |
Road cutting permission is to obtained for 26 locations. list and report attached |
AEE |
Duration & Sanction dates
Date of start of Project |
09/11/2020 |
Scheduled date of Completion of the Project |
31 Jul 2021 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
03 Mar 2020 |
TS Date |
07 Jul 2020 |