Project | KIIFB-TWSS-Replacement of existing damaged 315mm HDPE pipes with 350mm DI pipe from Observatory to Ayurveda College |
---|---|
Project Code | TVMKIIFB0418656P1 |
Type | Package |
Main Project | KIIFB-TWSS-Replacement of existing damaged 315mm HDPE pipes with 350mm DI pipe from Observatory to Ayurveda College |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | The proposal is to lay 3500m of 350mm DI-K9 pipe line to replace the damaged portions of 315mm HDPE pipes existing in Observatory/High Level Zone from OHSR at Observatory to Ayurveda college Junction |
Status | On-going |
District | Thiruvananthapuram |
Executing Office | Trivandrum Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 49300000 |
TS Number | TS/2018-2019/2018/8651 Dated: 18-09-2018 |
Technical specification | The proposal is to lay 3500m of 350mm DI-K9 pipe line to replace the damaged portions of 315mm HDPE pipes existing in Observatory/High Level Zone from OHSR at Observatory to Ayurveda college Junction |
Contractor | BABU THOMAS (Mob: 9446893887) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 30/09/2020 |
---|---|
Scheduled date of Completion as per agreement | 21 Aug 2020 |
Expected date of Completion | 31/03/2023 |
TS Date | 18 Sep 2018 |
---|---|
Estimate Approval | 18 Sep 2018 |
NIT Approval | 03 Jan 2019 |
Tender Closing | 21 Feb 2019 |
Price bid opening | 23 Feb 2019 |
Workorder Date | 30 Sep 2019 |
---|---|
NA | 22 Nov 2019 |
Thiruvananthapuram Project AE6 |
Date: 15/02/2024 |
Work in progress | 34% Completed
work was short closed at risk and cost of contractor vide No. KWA/PHC/D5/3065/2016 dated 05- 04-2023 of S E, the original work as cancelled and the tender authority has tendered the balance work. But even after retendering twice no offers were received. So the tender was cancelled. During the meeting convened by Ho'ble Minister for transport ,GoK on 25-07- 2023 has directed to tender the balance work immediately after recasting the estimate to three or more reaches under TS power of thee Executive Engineer..
Thiruvananthapuram Project AE7 |
Date: 26/07/2023 |
Work in progress | 34% Completed
work short closed vide S.E proceedings No.KWA/PHC/D5-/3065/2016- KIIFB dated 05/04/2023.