Laying transmission main and sewer networks in L block (Edathara)
Project |
Laying transmission main and sewer networks in L block (Edathara) |
Project Code |
TVMAMRUT1117694 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
Includes 6 sub projects |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
327000000
|
AS Number |
G.O(Rt) No.1243/2021 7/LSGD |
TS Amount (Rs) |
9670000 |
TS Number |
05/03/2022 |
Total Bill Submitted (Rs) |
78312528 |
Total Bill Paid (Rs) |
78312528 |
Population Benefitted |
61000 |
Capacity in MLD |
107.00 |
Actual Project Completion Date |
31 Mar 2023 |
Coverage |
Laying transmission main and sewer networks in L block (Edathara) |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-Laying transmission main and sewer network in Block L Edathara-collection and conveyance system- Laying Sewer network by HDD method from MH 10 towards KIIMS Hospital (Package VI) |
Trivandrum Project Dn |
|
2 |
Laying transmission main and sewer network in block L Edathara-collection & conveyance system-Supply & laying trunk main from stilling chamber at Udaya Garden to MH 89 |
Trivandrum Project Dn |
|
3 |
Laying transmission main and sewer networks in Block L (Edathara) -Package-5 Laying Sewer network in Block L from MH 110 to MH 117 |
Trivandrum Project Dn |
|
4 |
Laying transmission main and sewer networks in Block L (Edathara) -Package-5 Laying Sewer network in Block L from MH 110 to MH 150 |
Trivandrum Project Dn |
|
5 |
Laying transmission main and sewer networks in Block L (Edathara) -Package-5 Laying Sewer network in Block L from MH 117 to MH 122 |
Trivandrum Project Dn |
|
6 |
Laying trunk main from Stilling chamber at Pulayanarkotta to MH 10 of Pumping station at Edathara |
Trivandrum Project Dn |
|
7 |
Sewer network from Pettah Arasumoode junction to MH 7 Edathara pumping station |
Trivandrum Project Dn |
|
8 |
Supplying and laying sewer line through Pettah Venpalavattom road,Greenpark road and side of Amayizhanjan thodu and to MH 7 Edathara zone |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
23 Dec 2022 |
Construction of stilling chamber has been completed. RCC pipe laid 3199m out of 3204 m of 700,800,900 & 1000 mm dia pipe. 5m are to be laid of 1000 mm dia. Manholes construction and RCC pipe laying has been completed. Back filling ,MH cleaning, site clearing, reification of damaged drain and compound walls are in progress at Kunjuveedu. |
Thiruvananthapuram Project AE9 |
|
20 Dec 2022 |
Construction of stilling chamber has been completed. RCC pipe laid 3199m out of 3204 m of 700,800,900 & 1000 mm dia pipe. 5m are to be laid of 1000 mm dia. Manholes construction and RCC pipe laying has been completed. Back filling ,MH cleaning, site clearing, reification of damaged drain and compound walls are in progress at Kunjuveedu. |
Thiruvananthapuram Project AE9 |
|
13 Dec 2022 |
Construction of stilling chamber has been completed. RCC pipe laid 3199m out of 3204 m of 700,800,900 & 1000 mm dia pipe. 5m are to be laid of 1000 mm dia. Manholes construction has been completed. Pipe laying work and road leveling works are progress at Kunjuveedu. |
Thiruvananthapuram Project AE9 |
|
09 Dec 2022 |
Construction of stilling chamber has been completed. RCC pipe laid 3185.50 m out of 3204 m of 700,800,900 & 1000 mm dia pipe. 18.50 m are to be laid of 1000 mm dia. Manholes construction has been completed. Pipe laying work and road leveling works are progress at Kunjuveedu. |
Thiruvananthapuram Project AE9 |
|
07 Dec 2022 |
Construction of stilling chamber has been completed. RCC pipe laid 3180.50 m out of 3204 m of 700,800,900 & 1000 mm dia pipe. 23.50 m are to be laid of 1000 mm dia. Manholes construction has been completed. Pipe laying work at Kunjuveedu is in progress. |
Thiruvananthapuram Project AE9 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/03/2020 |
Scheduled date of Completion of the Project |
31 Mar 2021 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
02 Jul 2021 |
TS Date |
16 Jun 2018 |