DEPOSIT-UTILITY SHIFTING - KRFB MVPA - IDUKKI-Hill Highway improvement Peerumedu - Devikulam Road TWSS to Kattapana - Relaying pipes from 20 Acre to Idukki Kavala in Kattapana-Pipeline Work

Project DEPOSIT-UTILITY SHIFTING - KRFB MVPA - IDUKKI-Hill Highway improvement Peerumedu - Devikulam Road TWSS to Kattapana - Relaying pipes from 20 Acre to Idukki Kavala in Kattapana-Pipeline Work
Project Code IDKGOK112217611
Type Main project
Funding Agency GOK
Category Deposit Work
Type of scheme Water Supply
Scheme 4215-01-800-89
Description DEPOSIT-UTILITY SHIFTING - KRFB MVPA - IDUKKI-Hill Highway improvement Peerumedu - Devikulam Road TWSS to Kattapana - Relaying pipes from 20 Acre to Idukki Kavala in Kattapana-Pipeline Work
Status Completed
District Idukki
Executing Office Nedumkandam Sn
AS Amount (Rs) 2436000
AS Number KRFB-PMU/MVPA-IDK/HH-PD/2021
TS Amount (Rs) 2422000
TS Number WRD/KWA-CE(CR)/EST_TS/13987/2022_26_4_3
Total Bill Submitted (Rs) 1
Total Bill Paid (Rs) 1
Population Benefitted 500
Capacity in MLD 5.00
Actual Project Completion Date 30 Nov 2024
Coverage Relaying pipes from 20 Acre to Idukki Kavala in Kattapana-

Packages

No. Project Name Location View
1 DEPOSIT-UTILITY SHIFTING - KRFB MVPA - IDUKKI-Hill Highway improvement Peerumedu - Devikulam Road TWSS to Kattapana - Relaying pipes from 20 Acre to Idukki Kavala in Kattapana-Pipeline Work Nedumkandam Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Nov 2024 Work completed on 17.11.2024 Painavu PH Sub Dn AEE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 18/05/2023
Scheduled date of Completion of the Project 17 Nov 2024
Expected date of Completion 17/11/2024

Processing Dates

AS Date 01 Nov 2022
TS Date 25 Apr 2023