Jal Jeevan Mission (JJM)-WSS to Peravoor &adjoining Panchayths(Peravoor,Muzhakunnu,Kolayad, Chittariparamba,Aralam and Ayyankunnu) - Laying Distribution Network and providing FHTCs-Zone-V

Project Jal Jeevan Mission (JJM)-WSS to Peravoor &adjoining Panchayths(Peravoor,Muzhakunnu,Kolayad, Chittariparamba,Aralam and Ayyankunnu) - Laying Distribution Network and providing FHTCs-Zone-V
Project Code KNRJJM022214943
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Administrative Sanction from Government of Kerala vide Order G.O.(Rt)No.134/2022/WRD dated 23-02-2022 was issued under JAL JEEVAN MISSION (JJM) for the work JJM-Kannur District - Peravoor, Muzhakkunnu, Kolayad and Chittariparamba Panchayats- Water supply project to Peravoor , Muzhakkunnu, Payam and Ayyankunnu Panchayats - Laying distribution network and Providing FHTCs - Phase II-zone-V - Laying Distribution Network and Providing FHTCs In Aralam and Ayyankunnu Panchayaths
Status On-going
District Kannur
Executing Office Kannur Project Dn
AS Amount (Rs) 3687000000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 671700000
TS Number WRD/KWA-CE(NR)/EST_TS/1597/2022_5_2_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD 22.00
Actual Project Completion Date Date is not specified
Coverage Aralam Panchayath-75%,Ayyankunnu-25%

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-WSS to Peravoor &adjoining Panchayths(Peravoor,Muzhakunnu,Kolayad, Chittariparamba,Aralam and Ayyankunnu) - Laying Distribution Network and providing FHTCs-Zone-V Koothuparamba Project Sn No1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Mar 2025 Work in progress, 8200 m pipe laid Koothuparamba Project Sn No 1
04 Mar 2025 Work in progress, 7800 m pipe laid Koothuparamba Project Sn No 1
25 Feb 2025 Work in progress, 7800 m pipe laid Koothuparamba Project Sn No 1
22 Feb 2025 Work in progress, 7800 m pipe laid Koothuparamba Project Sn No 1
18 Feb 2025 Work in progress, 7800 m pipe laid Koothuparamba Project Sn No 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 28/05/2024
Scheduled date of Completion of the Project 28 Nov 2024
Expected date of Completion 28/04/2025

Processing Dates

AS Date 23 Feb 2022
TS Date 17 Jul 2023

Other details

Project Officers View