KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I-package-III-Part

Project KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I-package-III-Part
Project Code PKDKIIFB1118630P1
Type Package
Main Project KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I-package-III-part- supplying Laying commissioning and maintanence of of250mm DI K9 Clear Water Pumping Main along Kozhikode - Palakkad NH 966
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 8100000
TS Number TS/2019-2020/2019/18489 dtd 22.11.2019
Technical specification supplying Laying commissioning and maintanence of of250mm DI K9 Clear Water Pumping Main along Kozhikode - Palakkad NH 966
Contractor Robin mathew (Mob: 9400982877)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/12/2019
Scheduled date of Completion as per agreement 31 May 2020
Expected date of Completion 31/12/2023

Processing Dates

TS Date 22 Nov 2019
Estimate Approval 22 Nov 2019
NIT Approval 23 Nov 2019
Tender Closing 14 Dec 2019
Technichal Pre-Qualification 14 Dec 2019
Price bid opening 14 Dec 2019

Approval Dates

NA 07 Jan 2020
Workorder Date 24 Dec 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 2
Date: 10/11/2020

Work has been completed | 100% Completed

Bill prepared @ Rs.6712278.630.

Chittur Project Dn - AE 2
Date: 05/09/2020

Work in progress | 99% Completed

WORK COMPLETED -on 30/05/2020.