JJM - 2020-21- Thanniam Grama Pt - CWSS to KPCTA & WSS to Chazhur, Thanyam Anthikkad Panchayaths( Ongoing Scheme)- Providing FHTCs and Distribution Stengthening
Project |
JJM - 2020-21- Thanniam Grama Pt - CWSS to KPCTA & WSS to Chazhur, Thanyam Anthikkad Panchayaths( Ongoing Scheme)- Providing FHTCs and Distribution Stengthening |
Project Code |
TCRJJM08203889 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM - 2020-21- Thanniam Grama Pt - CWSS to KPCTA & WSS to Chazhur, Thanyam Anthikkad Panchayaths( Ongoing Scheme)- Providing FHTCs and Distribution Stengthening |
Status |
On-going |
District |
Thrissur |
Executing Office |
Cherpu PH Sn |
AS Amount (Rs) |
109000000
|
AS Number |
G.O.(Rt)No. 541/2020/WRD |
TS Amount (Rs) |
107600000 |
TS Number |
TS/2020-2021/2020/14210 |
Total Bill Submitted (Rs) |
34074287 |
Total Bill Paid (Rs) |
34074287 |
Population Benefitted |
10000 |
Capacity in MLD |
2.50 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Thanniam Grama Pt |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM - 2020-21- Thanniam Grama Pt - CWSS to KPCTA & WSS to Chazhur, Thanyam Anthikkad Panchayaths( Ongoing Scheme)- Providing FHTCs and Distribution Stengthening |
Cherpu PH Sn |
|
2 |
JJM-WSS to Thanniam Grama Panchayath-Road Restoration works(BM & BC) |
Cherpu PH Sn |
|
3 |
Thannyam GP - Providing fhtcs near public taps at Thannyam GP |
Cherpu PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
05 May 2024 |
Package 1: Work Completed, Package 2: Work order issued but work not started, Package 3: No work on site (36% work Completed) |
Cherpu AE |
|
02 May 2024 |
Package 1: Work Completed, Package 2: Work order issued but work not started, Package 3: No work on site (36% work Completed) |
Cherpu AE |
|
29 Apr 2024 |
Package 1: Work Completed, Package 2: Work order issued but work not started, Package 3: No work on site (36% work Completed) |
Cherpu AE |
|
26 Apr 2024 |
Package 1: Work Completed, Package 2: Work order issued but work not started, Package 3: No work on site (36% work Completed) |
Cherpu AE |
|
23 Apr 2024 |
Package 1: Work Completed, Package 2: Work order issued but work not started, Package 3: No work on site (36% work Completed) |
Cherpu AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
21/08/2020 |
Scheduled date of Completion of the Project |
20 May 2021 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
08 Nov 2020 |