Jal Jeevan Mission (JJM)-WSS to Edathala,Keezhmad,and Choornikara Panchayath-Providing Distribution system and FHTC in NAD road from Cochin Bank to Manalimukkau Jn in connection with Kinfra work in Edathala Panchayath-Part I-Providing Distribution system and FHTC-Pipeline Work
Jal Jeevan Mission (JJM)-WSS to Edathala,Keezhmad,and Choornikara Panchayath-Providing Distribution system and FHTC in NAD road from Cochin Bank to Manalimukkau Jn in connection with Kinfra work in Edathala Panchayath-Part I-Providing Distribution system and FHTC-Pipeline Work
Project Code
EKMJJM022213802
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-02
Description
Jal Jeevan Mission (JJM)-WSS to Edathala,Keezhmad,and Choornikara Panchayath-Providing Distribution system and FHTC in NAD road from Cochin Bank to Manalimukkau Jn in connection with Kinfra work in Edathala Panchayath-Part I-Providing Distribution system and FHTC-Pipeline Work
Jal Jeevan Mission (JJM)-WSS to Edathala,Keezhmad,and Choornikara Panchayath-Providing Distribution system and FHTC in NAD road from Cochin Bank to Manalimukkau Jn in connection with Kinfra work in Edathala Panchayath-Part I-Providing Distribution system and FHTC-Pipeline Work
Aluva Pipeline Sn
2
Jal Jeevan Mission (JJM)-WSS to Edathala, Keezhmad and Choornikkara Panchayath-Providing distribution system and FHTCs for Edathala Panchayath-Providing distribution network and FHTCs to Edathala Panchayath
Aluva Pipeline Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
24 Jun 2024
Agreement executed.160 mm PVC pipes ,400 mm DI pipes, 600 mm DI pipes and 350mm DI pipes supplied by contractor.First, second and third part bill submitted. PWD sanction received on 24/8/23.160 mm pvc 350 mm DI, 400 mm DI and 600mm DI pipelaying work in progress
Aluva AE I PL Sn
20 Jun 2024
Agreement executed.160 mm PVC pipes ,400 mm DI pipes, 600 mm DI pipes and 350mm DI pipes supplied by contractor.First, second and third part bill submitted. PWD sanction received on 24/8/23.160 mm pvc 350 mm DI, 400 mm DI and 600mm DI pipelaying work in progress
Aluva AE I PL Sn
17 Jun 2024
Agreement executed.160 mm PVC pipes ,400 mm DI pipes, 600 mm DI pipes and 350mm DI pipes supplied by contractor.First, second and third part bill submitted. PWD sanction received on 24/8/23.160 mm pvc 350 mm DI, 400 mm DI and 600mm DI pipelaying work in progress
Aluva AE I PL Sn
13 Jun 2024
Agreement executed.160 mm PVC pipes ,400 mm DI pipes, 600 mm DI pipes and 350mm DI pipes supplied by contractor.First, second and third part bill submitted. PWD sanction received on 24/8/23.160 mm pvc 350 mm DI, 400 mm DI and 600mm DI pipelaying work in progress
Aluva AE I PL Sn
10 Jun 2024
Agreement executed.160 mm PVC pipes ,400 mm DI pipes, 600 mm DI pipes and 350mm DI pipes supplied by contractor.First, second and third part bill submitted. PWD sanction received on 24/8/23.160 mm pvc 350 mm DI, 400 mm DI and 600mm DI pipelaying work in progress