| Project | Project-II-KIIFB -Replacing 500 mm Premo pipes by laying 500 mm DI -K9 pipes from C.V centre to Agastheswaram temple - Reach -1 |
|---|---|
| Project Code | TCRGOK04181359P2 |
| Type | Package |
| Main Project | KIIFB -Project-(TRAN2-WRD005-127):Replacement of Transmission Mains in Thrissur Circle |
| Funding Agency | KIIFB |
| Category | KIIFB |
| Type of scheme | Water Supply |
| Scheme | KIIFB |
| Description | CWSS to Nattika Firka - Replacing 500 mm Premo pipes by laying 500 mm DI -K9 pipes from C.V centre to Agastheswaram temple - Reach -1 |
| Status | On-going |
| District | Thrissur |
| Executing Office | Mathilakam PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | |
| TS Number | |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 01/01/2021 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 31/12/2023 |
| Mathilakam AE |
| Date: 08/10/2026 |
Work in progress | 90% Completed
700 mm DI pipe laying completed for 2503.56 out of 2500 m. Road restoration work completed 2100m- Bills under prepration, Time extension application upto 31.03.2027 submitted. .
| Mathilakam AE |
| Date: 24/09/2026 |
Work in progress | 90% Completed
700 mm DI pipe laying completed for 2503.56 out of 2500 m. Road restoration work completed 2100m- Bills under prepration.