JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system from WTP and Providing FHTCs -ZoneII &III

Project JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system from WTP and Providing FHTCs -ZoneII &III
Project Code KNRJJM092114201P1
Type Package
Main Project JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system and Providing FHTCs -ZoneII &III
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Laying Distribution line and providing 3600 FHTC .total distribution line proposed in this project is 153925m for main line and 27118 for laying rider line and parellel line for avoiding road crossing.
Status On-going
District Kannur
Executing Office Koothuparamba Project Sn No2
Agreement Number
Agreement Date
TS Amount (Rs) 417300000
TS Number WRD/KWA-CE(NR)/EST_TS/3689/2022_26_1_1
Technical specification Laying Distribution line and providing 3600 FHTC .total distribution line proposed in this project is 153925m for main line and 27118 for laying rider line and parellel line for avoiding road crossing.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/02/2023
Scheduled date of Completion as per agreement 14 Feb 2024
Expected date of Completion 14/02/2024

Processing Dates

TS Date 22 Nov 2022
Estimate Approval 22 Nov 2022
NIT Approval 03 Dec 2022
Tender Closing 17 Dec 2022
Technichal Pre-Qualification 31 Dec 2022
Price bid opening 05 Jan 2023

Approval Dates

Workorder Date 23 Jan 2023
NA 07 Feb 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Koothuparamba Proj AE 2
Date: 28/01/2025

Work in progress | 69% Completed

97000 m pipe laid and 1150 HTC given.

Koothuparamba Proj AE 2
Date: 24/01/2025

Work in progress | 69% Completed

97000 m pipe laid and 1150 HTC given.