Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Choondal Panchayath-Providing Distribution Network and FHTC to Choondal Panchayath

Project Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Choondal Panchayath-Providing Distribution Network and FHTC to Choondal Panchayath
Project Code TCRJJM052214449P1
Type Package
Main Project Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Choondal Panchayath-Providing Distribution Network and FHTC to Choondal Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Choondal Panchayath-Providing Distribution Network and FHTC to Choondal Panchayath
Status On-going
District Thrissur
Executing Office Nattika Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 409300000
TS Number WRD/KWA-CE(CR)/EST-TS/4162/2022-5_1_1
Technical specification Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Choondal Panchayath-Providing Distribution Network and FHTC to Choondal Panchayath

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/04/2023
Scheduled date of Completion as per agreement 17 Apr 2024
Expected date of Completion 17/04/2024

Processing Dates

TS Date 04 Nov 2022
Estimate Approval 04 Apr 2022
NIT Approval 18 May 2022
Tender Closing 22 Jun 2022
Technichal Pre-Qualification 02 Dec 2022
Price bid opening 30 Dec 2022

Approval Dates

Workorder Date 17 Apr 2023
NA 03 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nattika Project Dn
Date: 27/06/2024

Work in progress | 4% Completed

4945 m pipe laid out of 105148 m(90mm pvc-196m,75mm pvc-3161m,63mm pvc-1463m,50mm pvc-120m) Geo-Tagging = 179/5953 Nos and HTC given = 196/5953Nos,road Restoration-1623.5M/105148m..

Nattika Project Dn
Date: 26/06/2024

Work in progress | 4% Completed

4945 m pipe laid out of 105148 m(90mm pvc-196m,75mm pvc-3161m,63mm pvc-1463m,50mm pvc-120m) Geo-Tagging = 175/5953 Nos and HTC given = 196/5953Nos,road Restoration-1517.5M/105148m..