Project | Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Choondal Panchayath-Providing Distribution Network and FHTC to Choondal Panchayath |
---|---|
Project Code | TCRJJM052214449P1 |
Type | Package |
Main Project | Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Choondal Panchayath-Providing Distribution Network and FHTC to Choondal Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Choondal Panchayath-Providing Distribution Network and FHTC to Choondal Panchayath |
Status | On-going |
District | Thrissur |
Executing Office | Nattika Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 409300000 |
TS Number | WRD/KWA-CE(CR)/EST-TS/4162/2022-5_1_1 |
Technical specification | Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Choondal Panchayath-Providing Distribution Network and FHTC to Choondal Panchayath |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/04/2023 |
---|---|
Scheduled date of Completion as per agreement | 17 Apr 2024 |
Expected date of Completion | 17/04/2024 |
TS Date | 04 Nov 2022 |
---|---|
Estimate Approval | 04 Apr 2022 |
NIT Approval | 18 May 2022 |
Tender Closing | 22 Jun 2022 |
Technichal Pre-Qualification | 02 Dec 2022 |
Price bid opening | 30 Dec 2022 |
Workorder Date | 17 Apr 2023 |
---|---|
NA | 03 Jul 2023 |
Nattika Project Dn |
Date: 27/06/2024 |
Work in progress | 4% Completed
4945 m pipe laid out of 105148 m(90mm pvc-196m,75mm pvc-3161m,63mm pvc-1463m,50mm pvc-120m) Geo-Tagging = 179/5953 Nos and HTC given = 196/5953Nos,road Restoration-1623.5M/105148m..
Nattika Project Dn |
Date: 26/06/2024 |
Work in progress | 4% Completed
4945 m pipe laid out of 105148 m(90mm pvc-196m,75mm pvc-3161m,63mm pvc-1463m,50mm pvc-120m) Geo-Tagging = 175/5953 Nos and HTC given = 196/5953Nos,road Restoration-1517.5M/105148m..