Jal Jeevan Mission- Kannur District- Mayyil Grama Panchayath-WSS to Kolachery and adjoining Panchayaths- Phase 3- Zone I-Orapodi Area - Laying Distribution System and providing FHTCs

Project Jal Jeevan Mission- Kannur District- Mayyil Grama Panchayath-WSS to Kolachery and adjoining Panchayaths- Phase 3- Zone I-Orapodi Area - Laying Distribution System and providing FHTCs
Project Code KNRJJM092110788
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission- Kannur District- Mayyil Grama Panchayath-WSS to Kolachery and adjoining Panchayaths- Phase 3- Zone I-Orapodi Area - Laying Distribution System and providing FHTCs
Status Completed
District Kannur
Executing Office Kannur WS Dn
AS Amount (Rs) 476400000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 200100000
TS Number 15494/2021-2022
Total Bill Submitted (Rs) 29910080
Total Bill Paid (Rs) 29477002
Population Benefitted 5000
Capacity in MLD 13.40
Actual Project Completion Date 29 Nov 2025
Coverage Orapodi area of Mayyil panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission- Kannur District- Mayyil Grama Panchayath-WSS to Kolachery and adjoining Panchayaths- Phase 3- Zone I-Orapodi Area - Laying Distribution System and providing FHTCs Kolachery PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Jan 2026 Laid 160 mm 10 kg pvc pipe -1704 m,140mm 10 kg pvc pipe-2346 m, 110 mm 10 kg pvc pipe-4628 m, 110mm 8 kg pvc pipe-2652 m, 90mm 10 kg pvc pipe-20418 m, 90mm 8 kg pvc pipe-11943 m, 75mm 10 kg pvc pipe-21959 m, 75 mm 8 kg pvc pipe-8210.7 m, 63mm 10 kg pvc pipe-4193 m, 50mm 10 kg pvc pipe-3352 m, 90 mm PN 10 HDPE pipe- 9338 m, 90mm PN 8 HDPE- 3560 m, 75 mm PN 8 HDPE pipe-1664 m, 63 mm PN 10 HDPE pipe-1440 m House Connection Details:- FHTC-2634 Nos, HTC- 169 Nos. Final bill submitted. Kolachery PH Sn AE
13 Jan 2026 Laid 160 mm 10 kg pvc pipe -1704 m,140mm 10 kg pvc pipe-2346 m, 110 mm 10 kg pvc pipe-4628 m, 110mm 8 kg pvc pipe-2652 m, 90mm 10 kg pvc pipe-20418 m, 90mm 8 kg pvc pipe-11943 m, 75mm 10 kg pvc pipe-21959 m, 75 mm 8 kg pvc pipe-8210.7 m, 63mm 10 kg pvc pipe-4193 m, 50mm 10 kg pvc pipe-3352 m, 90 mm PN 10 HDPE pipe- 9338 m, 90mm PN 8 HDPE- 3560 m, 75 mm PN 8 HDPE pipe-1664 m, 63 mm PN 10 HDPE pipe-1440 m House Connection Details:- FHTC-2634 Nos, HTC- 169 Nos. Final bill submitted. Kolachery PH Sn AE
03 Jan 2026 Laid 160 mm 10 kg pvc pipe -1704 m,140mm 10 kg pvc pipe-2346 m, 110 mm 10 kg pvc pipe-4628 m, 110mm 8 kg pvc pipe-2652 m, 90mm 10 kg pvc pipe-20418 m, 90mm 8 kg pvc pipe-11943 m, 75mm 10 kg pvc pipe-21959 m, 75 mm 8 kg pvc pipe-8210.7 m, 63mm 10 kg pvc pipe-4193 m, 50mm 10 kg pvc pipe-3352 m, 90 mm PN 10 HDPE pipe- 9338 m, 90mm PN 8 HDPE- 3560 m, 75 mm PN 8 HDPE pipe-1664 m, 63 mm PN 10 HDPE pipe-1440 m House Connection Details:- FHTC-2634 Nos, HTC- 169 Nos. Final bill submitted. Kolachery PH Sn AE
03 Jan 2026 Laid 160 mm 10 kg pvc pipe -1704 m,140mm 10 kg pvc pipe-2346 m, 110 mm 10 kg pvc pipe-4628 m, 110mm 8 kg pvc pipe-2652 m, 90mm 10 kg pvc pipe-20418 m, 90mm 8 kg pvc pipe-11943 m, 75mm 10 kg pvc pipe-21959 m, 75 mm 8 kg pvc pipe-8210.7 m, 63mm 10 kg pvc pipe-4193 m, 50mm 10 kg pvc pipe-3352 m, 90 mm PN 10 HDPE pipe- 9338 m, 90mm PN 8 HDPE- 3560 m, 75 mm PN 8 HDPE pipe-1664 m, 63 mm PN 10 HDPE pipe-1440 m House Connection Details:- FHTC-2634 Nos, HTC- 169 Nos. Final bill submitted. Kolachery PH Sn AE
20 Dec 2025 Laid 160 mm 10 kg pvc pipe -1704 m,140mm 10 kg pvc pipe-2346 m, 110 mm 10 kg pvc pipe-4628 m, 110mm 8 kg pvc pipe-2652 m, 90mm 10 kg pvc pipe-20418 m, 90mm 8 kg pvc pipe-11943 m, 75mm 10 kg pvc pipe-21959 m, 75 mm 8 kg pvc pipe-8210.7 m, 63mm 10 kg pvc pipe-4193 m, 50mm 10 kg pvc pipe-3352 m, 90 mm PN 10 HDPE pipe- 9338 m, 90mm PN 8 HDPE- 3560 m, 75 mm PN 8 HDPE pipe-1664 m, 63 mm PN 10 HDPE pipe-1440 m House Connection Details:- FHTC-2634 Nos, HTC- 169 Nos. Final bill submitted. Kolachery PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 05/03/2022
Scheduled date of Completion of the Project 05 Sep 2022
Expected date of Completion 30/06/2023

Processing Dates

AS Date 18 Sep 2021
TS Date 16 Dec 2021

Other details